Skip to main content
R/DAR 2023

Finishing walls with Premium Acrylic Smooth exterior paint with Silicone additives of required shade

Old work (Two or more coats applied @ 1.43 ltr/ 10 sqm) over existing cement paint surface
Item number
13.112.1
Analysis basis
10 sqm
Priced inputs
5
Derived rate
₹131.30/ SQM
D-01/RATE ANALYSISITEM 13.112.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.112.1 (Finishing walls with Premium Acrylic Smooth exterior paint with Silicone additives of required shade Old work (Two or more coats applied @ 1.43 ltr/ 10 sqm) over existing cement paint surface) is derived from 5 priced inputs for 10 sqm and works out to ₹131.30 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 13.112.1DETAIL OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8506MATPremium Acrylic exterior paintlitre1.43250.00357.50
9977MATCarriage of materialL.S.1.042.272.36
0131LABPainterday0.46816.00375.36
0115LABCoolieday0.23736.00169.28
9999MATSundries for brushes,sand paper,scaffolding etcL.S.8.062.2718.30
BUILD-UP TO RATE
TOTAL
922.80
Add 1 % Water charges on “W”
+9.23
TOTAL
932.03
Add GST on “X” (multiplying factor 0.2127)
+198.24
TOTAL
1,130.27
Add 15% CPOH on “Y”
+169.54
TOTAL
1,299.81
Add Cess @ 1% on “Z”
+13.00
Cost of 10.00 sqm
1,312.81
Cost of 1.00 sqm
131.28
SAY
₹131.30
D-02/SOURCEPRINTED PAGE 1031
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1031

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1031. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSFINISHING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.