Painting with acid proof paint of approved brand and manufacture of required colour to give an even shade

One or more coats on old work
Item number
13.101.1
Analysis basis
10 sqm
Priced inputs
7
Derived rate
₹107.25/ SQM
D-01/RATE ANALYSISITEM 13.101.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.101.1 (Painting with acid proof paint of approved brand and manufacture of required colour to give an even shade : One or more coats on old work) is derived from 7 priced inputs for 10 sqm and works out to ₹107.25 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 13.101.1DETAIL OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0827MATAcid proof paint (chocolate or black)litre0.7225.00157.50
9977MATCarriage of paintL.S.0.522.271.18
9999MATPutty etcL.S.2.732.276.20
0131LABPainterday0.36816.00293.76
0115LABCoolieday0.36736.00264.96
9999MATBrushes, sand paper etcL.S.5.332.2712.10
9999MATSundriesL.S.8.062.2718.30
BUILD-UP TO RATE
TOTAL
754.00
Add 1 % Water charges on “W”
+7.54
TOTAL
761.54
Add GST on “X” (multiplying factor 0.2127)
+161.98
TOTAL
923.52
Add 15% CPOH on “Y”
+138.53
TOTAL
1,062.05
Add Cess @ 1% on “Z”
+10.62
Cost of 10.00 sqm
1,072.67
Cost of 1.00 sqm
107.27
SAY
₹107.25
D-02/SOURCEPRINTED PAGE 1025
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1025

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1025. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.