Painting with black anti-corrosive bitumastic paint of approved brand and manufacture to give an even shade

One or more coats on old work
Item number
13.102.1
Analysis basis
10 sqm
Priced inputs
6
Derived rate
₹93.70/ SQM
D-01/RATE ANALYSISITEM 13.102.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.102.1 (Painting with black anti-corrosive bitumastic paint of approved brand and manufacture to give an even shade : One or more coats on old work) is derived from 6 priced inputs for 10 sqm and works out to ₹93.70 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 13.102.1DETAIL OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0828MATAnticorrosive bituminous paint (black)litre0.57120.0068.40
9977MATCarriageL.S.0.522.271.18
0131LABPainterday0.36816.00293.76
0115LABCoolieday0.36736.00264.96
9999MATPutty, brushes, sand paper etcL.S.5.332.2712.10
9999MATSundriesL.S.8.062.2718.30
BUILD-UP TO RATE
TOTAL
658.70
Add 1 % Water charges on “W”
+6.59
TOTAL
665.29
Add GST on “X” (multiplying factor 0.2127)
+141.51
TOTAL
806.80
Add 15% CPOH on “Y”
+121.02
TOTAL
927.82
Add Cess @ 1% on “Z”
+9.28
Cost of 10.00 sqm
937.10
Cost of 1.00 sqm
93.71
SAY
₹93.70
D-02/SOURCEPRINTED PAGE 1025
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1025

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1025. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.