Skip to main content
R/DAR 2023

Painting with aluminium paint of approved brand and manufacture to give an even shade

One or more coats on old work
Item number
13.100.1
Analysis basis
10 sqm
Priced inputs
7
Derived rate
₹96.00/ SQM
D-01/RATE ANALYSISITEM 13.100.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 13.100.1 (Painting with aluminium paint of approved brand and manufacture to give an even shade: One or more coats on old work) is derived from 7 priced inputs for 10 sqm and works out to ₹96.00 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 13.100.1DETAIL OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0826MATAluminium paintlitre0.46170.0078.20
9977MATCarriage of paint and materialL.S.0.522.271.18
9999MATPutty etcL.S.2.732.276.20
0131LABPainterday0.36816.00293.76
0115LABCoolieday0.36736.00264.96
9999MATBrushes, sand paper etcL.S.5.332.2712.10
9999MATSundriesL.S.8.062.2718.30
BUILD-UP TO RATE
TOTAL
674.70
Add 1 % Water charges on “W”
+6.75
TOTAL
681.45
Add GST on “X” (multiplying factor 0.2127)
+144.94
TOTAL
826.39
Add 15% CPOH on “Y”
+123.96
TOTAL
950.35
Add Cess @ 1% on “Z”
+9.50
Cost of 10.00 sqm
959.85
Cost of 1.00 sqm
95.99
SAY
₹96.00
D-02/SOURCEPRINTED PAGE 1024
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1024

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1024. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSFINISHING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.