Deduct for not rolling with power roller of minimum 8 tonnes for banking excavated earth in layers not exceeding 20 cm in depth
- Item number
- 2.4
- Analysis basis
- 10 cum
- Priced inputs
- 3
- Derived rate
- ₹5.25/ CUM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 2.4 (Deduct for not rolling with power roller of minimum 8 tonnes for banking excavated earth in layers not exceeding 20 cm in depth) is derived from 3 priced inputs for 10 cum and works out to ₹5.25 per cum after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0113 | LAB | Chowkidar | day | 0.008 | 736.00 | 5.89 |
| 0003 | MACH | Hire charges of Diesel Road Roller - 8 to 10 tonne | day | 0.008 | 3,350.00 | 26.80 |
| 9999 | MAT | Sundries | L.S. | 1.82 | 2.27 | 4.13 |
- TOTAL
- 36.82
- Add 1 % Water charges on “W”
- +0.37
- TOTAL
- 37.19
- Add GST on “X” (multiplying factor 0.2127)
- +7.91
- TOTAL
- 45.10
- Add 15% CPOH on “Y”
- +6.77
- TOTAL
- 51.87
- Add Cess @ 1% on “Z”
- +0.52
- Cost of 10 cum.
- 52.39
- Cost of 1 cum.
- 5.24
- SAY
- ₹5.25
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 94
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 94. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.