Deduct for not rolling with power roller of minimum 8 tonnes for banking excavated earth in layers not exceeding 20 cm in depth

Item number
2.4
Analysis basis
10 cum
Priced inputs
3
Derived rate
₹5.25/ CUM
D-01/RATE ANALYSISITEM 2.4

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 2.4 (Deduct for not rolling with power roller of minimum 8 tonnes for banking excavated earth in layers not exceeding 20 cm in depth) is derived from 3 priced inputs for 10 cum and works out to ₹5.25 per cum after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 2.4DETAILS OF COST FOR 10 CUM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0113LABChowkidarday0.008736.005.89
0003MACHHire charges of Diesel Road Roller - 8 to 10 tonneday0.0083,350.0026.80
9999MATSundriesL.S.1.822.274.13
BUILD-UP TO RATE
TOTAL
36.82
Add 1 % Water charges on “W”
+0.37
TOTAL
37.19
Add GST on “X” (multiplying factor 0.2127)
+7.91
TOTAL
45.10
Add 15% CPOH on “Y”
+6.77
TOTAL
51.87
Add Cess @ 1% on “Z”
+0.52
Cost of 10 cum.
52.39
Cost of 1 cum.
5.24
SAY
₹5.25
D-02/SOURCEPRINTED PAGE 94
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
94

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 94. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.