Deduct for not watering the excavated earth for banking
- Item number
- 2.5
- Analysis basis
- 10 cum
- Priced inputs
- 1
- Derived rate
- ₹14.25/ CUM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 2.5 (Deduct for not watering the excavated earth for banking) is derived from 1 priced inputs for 10 cum and works out to ₹14.25 per cum after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0057 | MACH | Water tanker 6 KL capacityWater Tanker 5 to 6 KL capacity | hour | 0.4 | 250.00 | 100.00 |
- TOTAL
- 100.00
- Add 1 % Water charges on “W”
- +1.00
- TOTAL
- 101.00
- Add GST on “X” (multiplying factor 0.2127)
- +21.48
- TOTAL
- 122.48
- Add 15% CPOH on “Y”
- +18.37
- TOTAL
- 140.85
- Add Cess @ 1% on “Z”
- +1.41
- Cost of 10 cum.
- 142.26
- Cost of 1 cum.
- 14.23
- SAY
- ₹14.25
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 95
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 95. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.