Deduct for not watering the excavated earth for banking

Item number
2.5
Analysis basis
10 cum
Priced inputs
1
Derived rate
₹14.25/ CUM
D-01/RATE ANALYSISITEM 2.5

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 2.5 (Deduct for not watering the excavated earth for banking) is derived from 1 priced inputs for 10 cum and works out to ₹14.25 per cum after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 2.5DETAILS OF COST FOR 10 CUM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0057MACHWater tanker 6 KL capacityWater Tanker 5 to 6 KL capacityhour0.4250.00100.00
BUILD-UP TO RATE
TOTAL
100.00
Add 1 % Water charges on “W”
+1.00
TOTAL
101.00
Add GST on “X” (multiplying factor 0.2127)
+21.48
TOTAL
122.48
Add 15% CPOH on “Y”
+18.37
TOTAL
140.85
Add Cess @ 1% on “Z”
+1.41
Cost of 10 cum.
142.26
Cost of 1 cum.
14.23
SAY
₹14.25
D-02/SOURCEPRINTED PAGE 95
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
95

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 95. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSEARTH WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.