Supply and stacking of Fly ash conforming to IRC58 at site, including carriage, loading , unloading & stacking up to any lead (measured stacks will be reduced by 20% for payment)
- Item number
- 2.37
- Analysis basis
- 1 cum
- Priced inputs
- 2
- Derived rate
- ₹281.05/ CUM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 2.37 (Supply and stacking of Fly ash conforming to IRC58 at site, including carriage, loading , unloading & stacking up to any lead (measured stacks will be reduced by 20% for payment)) is derived from 2 priced inputs for 1 cum and works out to ₹281.05 per cum after water charges, GST, CPOH and cess. The full build-up is below.
- Ref :- Based on DAR Item No : 1.1.1
- Labour and carriage
- (Available free of cost at thermal power plant
- at Baderpur power plant. Lead = 35 km)
- (1st Lead 0 to 5km)
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 1980 | MAT | FlyashFly ash | cum | 1 | 12.00 | 12.00 |
| 2262 | MAT | Carriage of Flyash | cum | 1 | 185.55 | 185.55 |
- TOTAL
- 197.55
- Add 1 % Water charges on “W”
- +1.98
- TOTAL
- 199.53
- Add GST on “X” (multiplying factor 0.2127)
- +42.44
- TOTAL
- 241.97
- Add 15% CPOH on “Y”
- +36.30
- TOTAL
- 278.27
- Add Cess @ 1% on “Z”
- +2.78
- Cost of 1 cum.
- 281.05
- SAY
- ₹281.05
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 138
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 138. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.