Skip to main content

CPWD Analysis of Rates · Earth Work

Extra for levelling & neatly dressing of disposed soil completely as directed by Engineerin-charge

Item number
2.36
Analysis basis
Details of cost for 10 cum.
Priced inputs
2
Derived rate
93.05 / cum

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 2.36 Extra for levelling & neatly dressing of disposed soil completely as directed by Engineerin-charge — is derived from 2 priced inputs for 10 cum and works out to ₹93.05 per cum after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
0128MateLabourday0.08816.0065.28
0115Beldar/ CoolieCoolieLabourday0.8736.00588.80
TOTAL
654.08
Add 1 % Water charges on “W”
6.54
TOTAL
660.62
Add GST on “X” (multiplying factor 0.2127)
140.51
TOTAL
801.13
Add 15% CPOH on “Y”
120.17
TOTAL
921.30
Add Cess @ 1% on “Z”
9.21
Cost of 10 cum.
930.51
Cost of 1 cum.
93.05
Say
93.05

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 138. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works