Filling with available fly ash and earth (excluding rock) in trenches or embankment in layers (each layer should not exceed 15 cm), with intermediate layer of compacted earth (Soil density of 98%) after every four layers of compacted depth of fly ash, sides & top layer of filling shall be done with earth having total minimum compacted thickness 30 cm or as decided by Engineer -in-charge, including compacting each layer by rolling/ ramming and watering, all complete as per drawing and direction of Engineer -in - charge
- Item number
- 2.38
- Analysis basis
- 10 cum
- Priced inputs
- 3
- Derived rate
- ₹308.20/ CUM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 2.38 (Filling with available fly ash and earth (excluding rock) in trenches or embankment in layers (each layer should not exceed 15 cm), with intermediate layer of compacted earth (Soil density of 98%) after every four layers of compacted depth of fly ash, sides & top layer of filling shall be done with earth having total minimum compacted thickness 30 cm or as decided by Engineer -in-charge, including compacting each layer by rolling/ ramming and watering, all complete as per drawing and direction of Engineer -in - charge) is derived from 3 priced inputs for 10 cum and works out to ₹308.20 per cum after water charges, GST, CPOH and cess. The full build-up is below.
- Ref :- Based on DAR Item No : 2.25
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0128 | LAB | Mate | day | 0.2 | 816.00 | 163.20 |
| 0115 | LAB | Coolie | day | 2.5 | 736.00 | 1,840.00 |
| 0101 | LAB | Bhisti | day | 0.2 | 816.00 | 163.20 |
- TOTAL
- 2,166.40
- Add 1 % Water charges on “W”
- +21.66
- TOTAL
- 2,188.06
- Add GST on “X” (multiplying factor 0.2127)
- +465.40
- TOTAL
- 2,653.46
- Add 15% CPOH on “Y”
- +398.02
- TOTAL
- 3,051.48
- Add Cess @ 1% on “Z”
- +30.51
- Cost of 10 cum.
- 3,081.99
- Cost of 1 cum.
- 308.20
- SAY
- ₹308.20
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 139
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 139. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.