CPWD Analysis of Rates · Earth Work

Filling with available fly ash and earth (excluding rock) in trenches or embankment in layers (each layer should not exceed 15 cm), with intermediate layer of compacted earth (Soil density of 98%) after every four layers of compacted depth of fly ash, sides & top layer of filling shall be done with earth having total minimum compacted thickness 30 cm or as decided by Engineer -in-charge, including compacting each layer by rolling/ ramming and watering, all complete as per drawing and direction of Engineer -in - charge

Item number
2.38
Analysis basis
Details of cost for 10 cum.
Priced inputs
3
Derived rate
308.20 / cum

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 2.38 Filling with available fly ash and earth (excluding rock) in trenches or embankment in layers (each layer should not exceed 15 cm), with intermediate layer of compacted earth (Soil density of 98%) after every four layers of compacted depth of fly ash, sides & top layer of filling shall be done with earth having total minimum compacted thickness 30 cm or as decided by Engineer -in-charge, including compacting each layer by rolling/ ramming and watering, all complete as per drawing and direction of Engineer -in - charge — is derived from 3 priced inputs for 10 cum and works out to ₹308.20 per cum after water charges, GST, CPOH and cess. The full build-up is below.

  • Ref :- Based on DAR Item No : 2.25
CodeInputUnitQuantityRate (INR)Amount (INR)
0128MateLabourday0.2816.00163.20
0115CoolieLabourday2.5736.001,840.00
0101BhistiLabourday0.2816.00163.20
TOTAL
2,166.40
Add 1 % Water charges on “W”
21.66
TOTAL
2,188.06
Add GST on “X” (multiplying factor 0.2127)
465.40
TOTAL
2,653.46
Add 15% CPOH on “Y”
398.02
TOTAL
3,051.48
Add Cess @ 1% on “Z”
30.51
Cost of 10 cum.
3,081.99
Cost of 1 cum.
308.20
Say
308.20

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 139. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.