CPWD Analysis of Rates · Earth Work

Diluting and injecting chemical emulsion for POST-CONSTRUCTIONAL anti-termite treatment (excluding the cost of chemical emulsion) : Treatment of existing masonry using chemical emulsion @ one litre per hole at 300 mm interval including drilling holes at 45 degree and plugging them with cement mortar 1:2 (1 cement : 2 coarse sand) to the full depth of the hole

With Chlorpyriphos/Lindane E.C. 20% with 1% concentration

Item number
2.35.4.1
Analysis basis
Details of cost for 10 metres
Priced inputs
3
Derived rate
43.00 / metres

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 2.35.4.1 Diluting and injecting chemical emulsion for POST-CONSTRUCTIONAL anti-termite treatment (excluding the cost of chemical emulsion) : Treatment of existing masonry using chemical emulsion @ one litre per hole at 300 mm interval including drilling holes at 45 degree and plugging them with cement mortar 1:2 (1 cement : 2 coarse sand) to the full depth of the hole : With Chlorpyriphos/Lindane E.C. 20% with 1% concentration — is derived from 3 priced inputs for 10 metres and works out to ₹43.00 per metres after water charges, GST, CPOH and cess. The full build-up is below.

  • No. of holes 10.0/0.30 = 33.33+1 = 34.33
  • holes. Say 34 holes
  • chlorpyriphos 1% concentration required =
  • 34x1.0 = 34.00 litres
  • Chlorpyriphos 20% E.C. required 34.00/20 =
  • 1.70 litres
  • Chlorpyriphos 20% E.C. / Lindane 20% E.C.
  • 1.7 litres (to be supplied free of cost)
CodeInputUnitQuantityRate (INR)Amount (INR)
0114BeldarLabourday0.3736.00220.80
0124Mason 2nd classMason 2nd classLabourday0.05816.0040.80
9999Sundries, rent of pump etc.MaterialL.S.17.942.2740.72
TOTAL
302.32
Add 1 % Water charges on “W”
3.02
TOTAL
305.34
Add GST on “X” (multiplying factor 0.2127)
64.95
TOTAL
370.29
Add 15% CPOH on “Y”
55.54
TOTAL
425.83
Add Cess @ 1% on “Z”
4.26
Cost for 10 metres
430.09
Cost for 1 metre
43.01
Say
43.00

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 136. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.