CPWD Analysis of Rates · Earth Work
Diluting and injecting chemical emulsion for POST-CONSTRUCTIONAL anti-termite treatment (excluding the cost of chemical emulsion) : Treatment of existing masonry using chemical emulsion @ one litre per hole at 300 mm interval including drilling holes at 45 degree and plugging them with cement mortar 1:2 (1 cement : 2 coarse sand) to the full depth of the hole
With Chlorpyriphos/Lindane E.C. 20% with 1% concentration
- Item number
- 2.35.4.1
- Analysis basis
- Details of cost for 10 metres
- Priced inputs
- 3
- Derived rate
- ₹43.00 / metres
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 2.35.4.1 — Diluting and injecting chemical emulsion for POST-CONSTRUCTIONAL anti-termite treatment (excluding the cost of chemical emulsion) : Treatment of existing masonry using chemical emulsion @ one litre per hole at 300 mm interval including drilling holes at 45 degree and plugging them with cement mortar 1:2 (1 cement : 2 coarse sand) to the full depth of the hole : With Chlorpyriphos/Lindane E.C. 20% with 1% concentration — is derived from 3 priced inputs for 10 metres and works out to ₹43.00 per metres after water charges, GST, CPOH and cess. The full build-up is below.
- No. of holes 10.0/0.30 = 33.33+1 = 34.33
- holes. Say 34 holes
- chlorpyriphos 1% concentration required =
- 34x1.0 = 34.00 litres
- Chlorpyriphos 20% E.C. required 34.00/20 =
- 1.70 litres
- Chlorpyriphos 20% E.C. / Lindane 20% E.C.
- 1.7 litres (to be supplied free of cost)
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0114 | BeldarLabour | day | 0.3 | 736.00 | 220.80 |
| 0124 | Mason 2nd classMason 2nd classLabour | day | 0.05 | 816.00 | 40.80 |
| 9999 | Sundries, rent of pump etc.Material | L.S. | 17.94 | 2.27 | 40.72 |
- TOTAL
- 302.32
- Add 1 % Water charges on “W”
- 3.02
- TOTAL
- 305.34
- Add GST on “X” (multiplying factor 0.2127)
- 64.95
- TOTAL
- 370.29
- Add 15% CPOH on “Y”
- 55.54
- TOTAL
- 425.83
- Add Cess @ 1% on “Z”
- 4.26
- Cost for 10 metres
- 430.09
- Cost for 1 metre
- 43.01
- Say
- 43.00
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 136. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.