Diluting and injecting chemical emulsion for POST-CONSTRUCTIONAL anti-termite treatment (excluding the cost of chemical emulsion) : Treatment of soil under existing floors using chemical emulsion @ one litre per hole, 300 mm apart including drilling 12 mm diameter holes and plugging with cement mortar 1 :2 (1 cement : 2 Coarse sand) to match the existing floor
- Item number
- 2.35.3.1
- Analysis basis
- 9 sqm
- Priced inputs
- 3
- Derived rate
- ₹310.05/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 2.35.3.1 (Diluting and injecting chemical emulsion for POST-CONSTRUCTIONAL anti-termite treatment (excluding the cost of chemical emulsion) : Treatment of soil under existing floors using chemical emulsion @ one litre per hole, 300 mm apart including drilling 12 mm diameter holes and plugging with cement mortar 1 :2 (1 cement : 2 Coarse sand) to match the existing floor: With Chlorpyriphos/Lindane E.C. 20% with 1% concentration) is derived from 3 priced inputs for 9 sqm and works out to ₹310.05 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- No. of holes - 100 nos.
- Chlorpyriphos 1% required 100x1 litre = 100 litres
- Chlorpyriphos 20% E.C. = 100/20 = 5.0 litres
- Chlorpyriphos 20% E.C. / Lindane 20% E.C.
- 5 litres (to be supplied free of cost)
- (For making holes & spraying)
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0114 | LAB | Beldar | day | 2 | 736.00 | 1,472.00 |
| 0124 | LAB | Mason 2nd classMason 2nd class | day | 0.5 | 816.00 | 408.00 |
| 9999 | MAT | Sundries, rent of sprayer and mortar | L.S. | 35.88 | 2.27 | 81.45 |
- TOTAL
- 1,961.45
- Add 1 % Water charges on “W”
- +19.61
- TOTAL
- 1,981.06
- Add GST on “X” (multiplying factor 0.2127)
- +421.37
- TOTAL
- 2,402.43
- Add 15% CPOH on “Y”
- +360.36
- TOTAL
- 2,762.79
- Add Cess @ 1% on “Z”
- +27.63
- Cost for 9 square metre
- 2,790.42
- Cost per square metre
- 310.05
- SAY
- ₹310.05
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 136
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 136. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.