CPWD Analysis of Rates · Earth Work

Diluting and injecting chemical emulsion for POST-CONSTRUCTIONAL anti-termite treatment (excluding the cost of chemical emulsion) : Treatment of soil under existing floors using chemical emulsion @ one litre per hole, 300 mm apart including drilling 12 mm diameter holes and plugging with cement mortar 1 :2 (1 cement : 2 Coarse sand) to match the existing floor

With Chlorpyriphos/Lindane E.C. 20% with 1% concentration

Item number
2.35.3.1
Analysis basis
Details of cost for 9 sqm. (3 metre x 3 metre)
Priced inputs
3
Derived rate
310.05 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 2.35.3.1 Diluting and injecting chemical emulsion for POST-CONSTRUCTIONAL anti-termite treatment (excluding the cost of chemical emulsion) : Treatment of soil under existing floors using chemical emulsion @ one litre per hole, 300 mm apart including drilling 12 mm diameter holes and plugging with cement mortar 1 :2 (1 cement : 2 Coarse sand) to match the existing floor: With Chlorpyriphos/Lindane E.C. 20% with 1% concentration — is derived from 3 priced inputs for 9 sqm and works out to ₹310.05 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • No. of holes - 100 nos.
  • Chlorpyriphos 1% required 100x1 litre = 100 litres
  • Chlorpyriphos 20% E.C. = 100/20 = 5.0 litres
  • Chlorpyriphos 20% E.C. / Lindane 20% E.C.
  • 5 litres (to be supplied free of cost)
  • (For making holes & spraying)
CodeInputUnitQuantityRate (INR)Amount (INR)
0114BeldarLabourday2736.001,472.00
0124Mason 2nd classMason 2nd classLabourday0.5816.00408.00
9999Sundries, rent of sprayer and mortarMaterialL.S.35.882.2781.45
TOTAL
1,961.45
Add 1 % Water charges on “W”
19.61
TOTAL
1,981.06
Add GST on “X” (multiplying factor 0.2127)
421.37
TOTAL
2,402.43
Add 15% CPOH on “Y”
360.36
TOTAL
2,762.79
Add Cess @ 1% on “Z”
27.63
Cost for 9 square metre
2,790.42
Cost per square metre
310.05
Say
310.05

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 136. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.