CPWD Analysis of Rates · Earth Work
Diluting and injecting chemical emulsion for POST-CONSTRUCTIONAL anti-termite treatment (excluding the cost of chemical emulsion) : Treatment of soil under existing floors using chemical emulsion @ one litre per hole, 300 mm apart including drilling 12 mm diameter holes and plugging with cement mortar 1 :2 (1 cement : 2 Coarse sand) to match the existing floor
With Chlorpyriphos/Lindane E.C. 20% with 1% concentration
- Item number
- 2.35.3.1
- Analysis basis
- Details of cost for 9 sqm. (3 metre x 3 metre)
- Priced inputs
- 3
- Derived rate
- ₹310.05 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 2.35.3.1 — Diluting and injecting chemical emulsion for POST-CONSTRUCTIONAL anti-termite treatment (excluding the cost of chemical emulsion) : Treatment of soil under existing floors using chemical emulsion @ one litre per hole, 300 mm apart including drilling 12 mm diameter holes and plugging with cement mortar 1 :2 (1 cement : 2 Coarse sand) to match the existing floor: With Chlorpyriphos/Lindane E.C. 20% with 1% concentration — is derived from 3 priced inputs for 9 sqm and works out to ₹310.05 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- No. of holes - 100 nos.
- Chlorpyriphos 1% required 100x1 litre = 100 litres
- Chlorpyriphos 20% E.C. = 100/20 = 5.0 litres
- Chlorpyriphos 20% E.C. / Lindane 20% E.C.
- 5 litres (to be supplied free of cost)
- (For making holes & spraying)
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0114 | BeldarLabour | day | 2 | 736.00 | 1,472.00 |
| 0124 | Mason 2nd classMason 2nd classLabour | day | 0.5 | 816.00 | 408.00 |
| 9999 | Sundries, rent of sprayer and mortarMaterial | L.S. | 35.88 | 2.27 | 81.45 |
- TOTAL
- 1,961.45
- Add 1 % Water charges on “W”
- 19.61
- TOTAL
- 1,981.06
- Add GST on “X” (multiplying factor 0.2127)
- 421.37
- TOTAL
- 2,402.43
- Add 15% CPOH on “Y”
- 360.36
- TOTAL
- 2,762.79
- Add Cess @ 1% on “Z”
- 27.63
- Cost for 9 square metre
- 2,790.42
- Cost per square metre
- 310.05
- Say
- 310.05
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 136. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works