Diluting and injecting chemical emulsion for POST-CONSTRUCTIONAL anti-termite treatment (excluding the cost of chemical emulsion) : Along the external wall below concrete or masonry apron using chemical emulsion @ 2.25 litres per linear metre including drilling and plugging holes etc.

With Chlorpyriphos/ Lindane E.C. 20% with 1% concentration
Item number
2.35.2.1
Analysis basis
10 metres
Priced inputs
2
Derived rate
₹53.45/ METRES
D-01/RATE ANALYSISITEM 2.35.2.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 2.35.2.1 (Diluting and injecting chemical emulsion for POST-CONSTRUCTIONAL anti-termite treatment (excluding the cost of chemical emulsion) : Along the external wall below concrete or masonry apron using chemical emulsion @ 2.25 litres per linear metre including drilling and plugging holes etc.: With Chlorpyriphos/ Lindane E.C. 20% with 1% concentration) is derived from 2 priced inputs for 10 metres and works out to ₹53.45 per metres after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Chlorpyriphos 1% concentration = 10x 2.25 =
  • 22.5 litres
  • Chlorpyriphos 20% required = 22.50/20 =
  • 1.125 litres
  • Chlorpyriphos 20% E.C. / Lindane 20% E.C.
  • 1.125 litres (to be supplied free of cost)
  • (for drilling holes and injecting chemical)
ANALYSIS OF RATES · ITEM 2.35.2.1DETAILS OF COST FOR 10 METRES
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0114LABBeldarday0.4736.00294.40
9999MATSundries and rent of a sprayer and mortar and making good the holesL.S.35.882.2781.45
BUILD-UP TO RATE
TOTAL
375.85
Add 1 % Water charges on “W”
+3.76
TOTAL
379.61
Add GST on “X” (multiplying factor 0.2127)
+80.74
TOTAL
460.35
Add 15% CPOH on “Y”
+69.05
TOTAL
529.40
Add Cess @ 1% on “Z”
+5.29
Cost for 10 metres
534.69
Cost for 1 metre
53.47
SAY
₹53.45
D-02/SOURCEPRINTED PAGE 135
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
135

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 135. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.