Diluting and injecting chemical emulsion for POST-CONSTRUCTIONAL anti-termite treatment (excluding the cost of chemical emulsion) : Along the external wall below concrete or masonry apron using chemical emulsion @ 2.25 litres per linear metre including drilling and plugging holes etc.
With Chlorpyriphos/ Lindane E.C. 20% with 1% concentration
- Item number
- 2.35.2.1
- Analysis basis
- Details of cost for 10 metres
- Priced inputs
- 2
- Derived rate
- ₹53.45 / metres
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 2.35.2.1 — Diluting and injecting chemical emulsion for POST-CONSTRUCTIONAL anti-termite treatment (excluding the cost of chemical emulsion) : Along the external wall below concrete or masonry apron using chemical emulsion @ 2.25 litres per linear metre including drilling and plugging holes etc.: With Chlorpyriphos/ Lindane E.C. 20% with 1% concentration — is derived from 2 priced inputs for 10 metres and works out to ₹53.45 per metres after water charges, GST, CPOH and cess. The full build-up is below.
- Chlorpyriphos 1% concentration = 10x 2.25 =
- 22.5 litres
- Chlorpyriphos 20% required = 22.50/20 =
- 1.125 litres
- Chlorpyriphos 20% E.C. / Lindane 20% E.C.
- 1.125 litres (to be supplied free of cost)
- (for drilling holes and injecting chemical)
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0114 | BeldarLabour | day | 0.4 | 736.00 | 294.40 |
| 9999 | Sundries and rent of a sprayer and mortar and making good the holesMaterial | L.S. | 35.88 | 2.27 | 81.45 |
- TOTAL
- 375.85
- Add 1 % Water charges on “W”
- 3.76
- TOTAL
- 379.61
- Add GST on “X” (multiplying factor 0.2127)
- 80.74
- TOTAL
- 460.35
- Add 15% CPOH on “Y”
- 69.05
- TOTAL
- 529.40
- Add Cess @ 1% on “Z”
- 5.29
- Cost for 10 metres
- 534.69
- Cost for 1 metre
- 53.47
- Say
- 53.45
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 135. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.