Felling trees of the girth (measured at a height of 1 m above ground level), including cutting of trunks and branches, removing the roots and stacking of serviceable material and disposal of unserviceable material
- Item number
- 2.33.3
- Analysis basis
- a tree
- Priced inputs
- 3
- Derived rate
- ₹11,020.15/ A TREE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 2.33.3 (Felling trees of the girth (measured at a height of 1 m above ground level), including cutting of trunks and branches, removing the roots and stacking of serviceable material and disposal of unserviceable material Beyond 120 cm girth upto and including 240 cm girth) is derived from 3 priced inputs for a tree and works out to ₹11,020.15 per a tree after water charges, GST, CPOH and cess. The full build-up is below.
- 180cm, average dia. 0.6m and length 7m
- quantity of wood- (22x06x0.60x7)/7x4 = 1.98
- cum.+ 20% branches = 0.40 cum. Total =
- 2.38 cum.
- Labour for cutting trees, removing roots from
- the soil and filling in pit & depressions:
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0114 | LAB | Beldar | day | 7 | 736.00 | 5,152.00 |
| 0115 | LAB | Coolie | day | 3.5 | 736.00 | 2,576.00 |
| 9999 | MAT | Sundries | L.S. | 8.06 | 2.27 | 18.30 |
- TOTAL
- 7,746.30
- Add 1 % Water charges on “W”
- +77.46
- TOTAL
- 7,823.76
- Add GST on “X” (multiplying factor 0.2127)
- +1,664.11
- TOTAL
- 9,487.87
- Add 15% CPOH on “Y”
- +1,423.18
- TOTAL
- 10,911.05
- Add Cess @ 1% on “Z”
- +109.11
- Cost of one tree
- 11,020.16
- SAY
- ₹11,020.15
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 133
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 133. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.