CPWD Analysis of Rates · Earth Work
Felling trees of the girth (measured at a height of 1 m above ground level), including cutting of trunks and branches, removing the roots and stacking of serviceable material and disposal of unserviceable material
Above 240 cm girth
- Item number
- 2.33.4
- Analysis basis
- Details of cost for a tree of average girth
- Priced inputs
- 3
- Derived rate
- ₹22,075.20 / a tree
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 2.33.4 — Felling trees of the girth (measured at a height of 1 m above ground level), including cutting of trunks and branches, removing the roots and stacking of serviceable material and disposal of unserviceable material Above 240 cm girth — is derived from 3 priced inputs for a tree and works out to ₹22,075.20 per a tree after water charges, GST, CPOH and cess. The full build-up is below.
- 300cm, average dia. 1m and length 10m
- quantity of wood- (22 x 1 x 1 x 10)/7x4 = 7.86
- cum + 20% Branches = 1.57 cum. Total =
- 9.43 cum.
- Labour for cutting trees, removing roots from
- the soil and filling in pit & depressions:
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0114 | BeldarLabour | day | 14 | 736.00 | 10,304.00 |
| 0115 | CoolieLabour | day | 7 | 736.00 | 5,152.00 |
| 9999 | SundriesMaterial | L.S. | 26.91 | 2.27 | 61.09 |
- TOTAL
- 15,517.09
- Add 1 % Water charges on “W”
- 155.17
- TOTAL
- 15,672.26
- Add GST on “X” (multiplying factor 0.2127)
- 3,333.49
- TOTAL
- 19,005.75
- Add 15% CPOH on “Y”
- 2,850.86
- TOTAL
- 21,856.61
- Add Cess @ 1% on “Z”
- 218.57
- Cost of one tree
- 22,075.18
- Say
- 22,075.20
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 134. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works