Felling trees of the girth (measured at a height of 1 m above ground level), including cutting of trunks and branches, removing the roots and stacking of serviceable material and disposal of unserviceable material
- Item number
- 2.33.4
- Analysis basis
- a tree
- Priced inputs
- 3
- Derived rate
- ₹22,075.20/ A TREE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 2.33.4 (Felling trees of the girth (measured at a height of 1 m above ground level), including cutting of trunks and branches, removing the roots and stacking of serviceable material and disposal of unserviceable material Above 240 cm girth) is derived from 3 priced inputs for a tree and works out to ₹22,075.20 per a tree after water charges, GST, CPOH and cess. The full build-up is below.
- 300cm, average dia. 1m and length 10m
- quantity of wood- (22 x 1 x 1 x 10)/7x4 = 7.86
- cum + 20% Branches = 1.57 cum. Total =
- 9.43 cum.
- Labour for cutting trees, removing roots from
- the soil and filling in pit & depressions:
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0114 | LAB | Beldar | day | 14 | 736.00 | 10,304.00 |
| 0115 | LAB | Coolie | day | 7 | 736.00 | 5,152.00 |
| 9999 | MAT | Sundries | L.S. | 26.91 | 2.27 | 61.09 |
- TOTAL
- 15,517.09
- Add 1 % Water charges on “W”
- +155.17
- TOTAL
- 15,672.26
- Add GST on “X” (multiplying factor 0.2127)
- +3,333.49
- TOTAL
- 19,005.75
- Add 15% CPOH on “Y”
- +2,850.86
- TOTAL
- 21,856.61
- Add Cess @ 1% on “Z”
- +218.57
- Cost of one tree
- 22,075.18
- SAY
- ₹22,075.20
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 134
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 134. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.