CPWD Analysis of Rates · Earth Work

Felling trees of the girth (measured at a height of 1 m above ground level), including cutting of trunks and branches, removing the roots and stacking of serviceable material and disposal of unserviceable material

Beyond 60 cm girth upto and including 120 cm girth

Item number
2.33.2
Analysis basis
Details of cost for a tree of average girth
Priced inputs
3
Derived rate
2,373.50 / a tree

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 2.33.2 Felling trees of the girth (measured at a height of 1 m above ground level), including cutting of trunks and branches, removing the roots and stacking of serviceable material and disposal of unserviceable material Beyond 60 cm girth upto and including 120 cm girth — is derived from 3 priced inputs for a tree and works out to ₹2,373.50 per a tree after water charges, GST, CPOH and cess. The full build-up is below.

  • 90cm, average dia. 0.3m and length 5m
  • quantity of wood- (22x0.30x0.30x5)/7x4 =
  • 0.35 cum + 20% branches = 0.07 cum. Total
  • = 0.42 cum
  • Labour for cutting trees, removing roots from
  • the soil and filling in pit & depressions:
CodeInputUnitQuantityRate (INR)Amount (INR)
0114BeldarLabourday1.5736.001,104.00
0115CoolieLabourday0.75736.00552.00
9999SundriesMaterialL.S.5.462.2712.39
TOTAL
1,668.39
Add 1 % Water charges on “W”
16.68
TOTAL
1,685.07
Add GST on “X” (multiplying factor 0.2127)
358.41
TOTAL
2,043.48
Add 15% CPOH on “Y”
306.52
TOTAL
2,350.00
Add Cess @ 1% on “Z”
23.50
Cost of one tree
2,373.50
Say
2,373.50

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 133. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.