Felling trees of the girth (measured at a height of 1 m above ground level), including cutting of trunks and branches, removing the roots and stacking of serviceable material and disposal of unserviceable material
- Item number
- 2.33.1
- Analysis basis
- one tree
- Priced inputs
- 3
- Derived rate
- ₹532.35/ ONE TREE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 2.33.1 (Felling trees of the girth (measured at a height of 1 m above ground level), including cutting of trunks and branches, removing the roots and stacking of serviceable material and disposal of unserviceable material Beyond 30 cm girth upto and including 60 cm girth) is derived from 3 priced inputs for one tree and works out to ₹532.35 per one tree after water charges, GST, CPOH and cess. The full build-up is below.
- average height 3m
- quantity of wood3.14/4x0.15x0.15x3 = 0.053 cum.
- Total = 0.064 cum.
- Labour for cutting in trees removing the
- roots from the soil and then filling in Pit and
- depresions.
- Add 20% for branches = 0.011 cum.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0114 | LAB | Beldar | day | 0.33 | 736.00 | 242.88 |
| 0115 | LAB | Coolie | day | 0.17 | 736.00 | 125.12 |
| 9999 | MAT | Sundries | L.S. | 2.73 | 2.27 | 6.20 |
- TOTAL
- 374.20
- Add 1 % Water charges on “W”
- +3.74
- TOTAL
- 377.94
- Add GST on “X” (multiplying factor 0.2127)
- +80.39
- TOTAL
- 458.33
- Add 15% CPOH on “Y”
- +68.75
- TOTAL
- 527.08
- Add Cess @ 1% on “Z”
- +5.27
- Cost of one tree
- 532.35
- SAY
- ₹532.35
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 132
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 132. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.