Skip to main content

CPWD Analysis of Rates · Earth Work

Felling trees of the girth (measured at a height of 1 m above ground level), including cutting of trunks and branches, removing the roots and stacking of serviceable material and disposal of unserviceable material

Beyond 30 cm girth upto and including 60 cm girth

Item number
2.33.1
Analysis basis
Details of cost for one tree of 15cm dia and
Priced inputs
3
Derived rate
532.35 / one tree

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 2.33.1 Felling trees of the girth (measured at a height of 1 m above ground level), including cutting of trunks and branches, removing the roots and stacking of serviceable material and disposal of unserviceable material Beyond 30 cm girth upto and including 60 cm girth — is derived from 3 priced inputs for one tree and works out to ₹532.35 per one tree after water charges, GST, CPOH and cess. The full build-up is below.

  • average height 3m
  • quantity of wood3.14/4x0.15x0.15x3 = 0.053 cum.
  • Total = 0.064 cum.
  • Labour for cutting in trees removing the
  • roots from the soil and then filling in Pit and
  • depresions.
  • Add 20% for branches = 0.011 cum.
CodeInputUnitQuantityRate (INR)Amount (INR)
0114BeldarLabourday0.33736.00242.88
0115CoolieLabourday0.17736.00125.12
9999SundriesMaterialL.S.2.732.276.20
TOTAL
374.20
Add 1 % Water charges on “W”
3.74
TOTAL
377.94
Add GST on “X” (multiplying factor 0.2127)
80.39
TOTAL
458.33
Add 15% CPOH on “Y”
68.75
TOTAL
527.08
Add Cess @ 1% on “Z”
5.27
Cost of one tree
532.35
Say
532.35

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 132. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works