Felling trees of the girth (measured at a height of 1 m above ground level), including cutting of trunks and branches, removing the roots and stacking of serviceable material and disposal of unserviceable material

Beyond 30 cm girth upto and including 60 cm girth
Item number
2.33.1
Analysis basis
one tree
Priced inputs
3
Derived rate
₹532.35/ ONE TREE
D-01/RATE ANALYSISITEM 2.33.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 2.33.1 (Felling trees of the girth (measured at a height of 1 m above ground level), including cutting of trunks and branches, removing the roots and stacking of serviceable material and disposal of unserviceable material Beyond 30 cm girth upto and including 60 cm girth) is derived from 3 priced inputs for one tree and works out to ₹532.35 per one tree after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • average height 3m
  • quantity of wood3.14/4x0.15x0.15x3 = 0.053 cum.
  • Total = 0.064 cum.
  • Labour for cutting in trees removing the
  • roots from the soil and then filling in Pit and
  • depresions.
  • Add 20% for branches = 0.011 cum.
ANALYSIS OF RATES · ITEM 2.33.1DETAILS OF COST FOR ONE TREE OF 15CM DIA AND
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0114LABBeldarday0.33736.00242.88
0115LABCoolieday0.17736.00125.12
9999MATSundriesL.S.2.732.276.20
BUILD-UP TO RATE
TOTAL
374.20
Add 1 % Water charges on “W”
+3.74
TOTAL
377.94
Add GST on “X” (multiplying factor 0.2127)
+80.39
TOTAL
458.33
Add 15% CPOH on “Y”
+68.75
TOTAL
527.08
Add Cess @ 1% on “Z”
+5.27
Cost of one tree
532.35
SAY
₹532.35
D-02/SOURCEPRINTED PAGE 132
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
132

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 132. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSEARTH WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.