Skip to main content
R/DAR 2023

Supplying and filling in plinth with sand under floors, including watering, ramming, consolidating and dressing complete

Item number
2.27
Analysis basis
10 cum
Priced inputs
4
Derived rate
₹2,123.75/ CUM
D-01/RATE ANALYSISITEM 2.27

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 2.27 (Supplying and filling in plinth with sand under floors, including watering, ramming, consolidating and dressing complete) is derived from 4 priced inputs for 10 cum and works out to ₹2,123.75 per cum after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 2.27DETAILS OF COST FOR 10 CUM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
6501MATSand zone V (Jamuna)cum101,320.0013,200.00
0114LABBeldarday0.89736.00655.04
0115LABCoolieday1.07736.00787.52
0101LABBhistiday0.35816.00285.60
BUILD-UP TO RATE
TOTAL
14,928.16
Add 1 % Water charges on “W”
+149.28
TOTAL
15,077.44
Add GST on “X” (multiplying factor 0.2127)
+3,206.97
TOTAL
18,284.41
Add 15% CPOH on “Y”
+2,742.66
TOTAL
21,027.07
Add Cess @ 1% on “Z”
+210.27
Cost of 10 cum.
21,237.34
Cost of 1 cum.
2,123.73
SAY
₹2,123.75
D-02/SOURCEPRINTED PAGE 129
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
129

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 129. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSEARTH WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.