Extra for every additional lift of 1.5 m or part thereof in excavation / banking excavated or stacked materials

Ordinary or hard rock
Item number
2.26.2
Analysis basis
10 cum
Priced inputs
2
Derived rate
₹227.40/ CUM
D-01/RATE ANALYSISITEM 2.26.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 2.26.2 (Extra for every additional lift of 1.5 m or part thereof in excavation / banking excavated or stacked materials Ordinary or hard rock) is derived from 2 priced inputs for 10 cum and works out to ₹227.40 per cum after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 2.26.2DETAILS OF COST FOR 10 CUM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0128LABMateday0.2816.00163.20
0114LABBeldarday1.95736.001,435.20
BUILD-UP TO RATE
TOTAL
1,598.40
Add 1 % Water charges on “W”
+15.98
TOTAL
1,614.38
Add GST on “X” (multiplying factor 0.2127)
+343.38
TOTAL
1,957.76
Add 15% CPOH on “Y”
+293.66
TOTAL
2,251.42
Add Cess @ 1% on “Z”
+22.51
Cost of 10 cum.
2,273.93
Cost of 1 cum.
227.39
SAY
₹227.40
D-02/SOURCEPRINTED PAGE 128
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
128

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 128. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.