Skip to main content
R/DAR 2023

Extra for every additional lift of 1.5 m or part thereof in excavation / banking excavated or stacked materials

All kinds of soil
Item number
2.26.1
Analysis basis
10 cum
Priced inputs
2
Derived rate
₹126.80/ CUM
D-01/RATE ANALYSISITEM 2.26.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 2.26.1 (Extra for every additional lift of 1.5 m or part thereof in excavation / banking excavated or stacked materials All kinds of soil) is derived from 2 priced inputs for 10 cum and works out to ₹126.80 per cum after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 2.26.1DETAILS OF COST FOR 10 CUM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0128LABMateday0.1816.0081.60
0114LABBeldarday1.1736.00809.60
BUILD-UP TO RATE
TOTAL
891.20
Add 1 % Water charges on “W”
+8.91
TOTAL
900.11
Add GST on “X” (multiplying factor 0.2127)
+191.45
TOTAL
1,091.56
Add 15% CPOH on “Y”
+163.73
TOTAL
1,255.29
Add Cess @ 1% on “Z”
+12.55
Cost of 10 cum.
1,267.84
Cost of 1 cum.
126.78
SAY
₹126.80
D-02/SOURCEPRINTED PAGE 128
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
128

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 128. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSEARTH WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.