R/DAR 2023

Excavating, supplying, stacking and filling of local earth (including royalty) by mechanical transport upto a lead of 5km also including ramming and watering of the earth in layers not exceeding 20 cm in foundation trenches, plinth, sides of foundation etc. complete for all lift

Item number
2.25(a)
Analysis basis
10 cum
Priced inputs
7
Derived rate
₹700.50/ CUM
D-01/RATE ANALYSISITEM 2.25(a)

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 2.25(a) (Excavating, supplying, stacking and filling of local earth (including royalty) by mechanical transport upto a lead of 5km also including ramming and watering of the earth in layers not exceeding 20 cm in foundation trenches, plinth, sides of foundation etc. complete for all lift) is derived from 7 priced inputs for 10 cum and works out to ₹700.50 per cum after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Carriage of materials upto 5 km
ANALYSIS OF RATES · ITEM 2.25(a)DETAILS OF COST FOR 10 CUM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0020MACHHydraulic Excavator (3D) with driver and fuel. (Cofficient from item No 2.6.1)Hydraulic Excavator (3D) with driver and fuelday0.087,850.00628.00
0128LABMateday0.04816.0032.64
0114LABBeldar (1/2x0.89=0.45 day)Beldarday0.45736.00331.20
0115LABCoolieday1.208736.00889.09
0101LABBhistiday0.18816.00146.88
SUBRate as per item No 1.1.2 of SH:1 carriage of materials including loading, unloading and stackingRate as per item 1.1.2cum10326.683,266.80
0979MATRoyalty for good earthcum1060.00600.00
BUILD-UP TO RATE
TOTAL
5,894.61
Add 1 % Water charges on “W-A”
+26.28
TOTAL
5,920.89
Add GST on “X-A” (multiplying factor 0.2127)
+564.52
TOTAL
6,485.41
Add 15% CPOH on “Y-A”
+482.79
TOTAL
6,968.20
Add Cess @ 1% on “Z-A”
+37.01
Cost of 10 cum
7,005.21
Cost of 1 cum
700.52
SAY
₹700.50
D-02/SOURCEPRINTED PAGE 127
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
127

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 127. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.