CPWD Analysis of Rates · Earth Work

Excavating, supplying, stacking and filling of local earth (including royalty) by mechanical transport upto a lead of 5km also including ramming and watering of the earth in layers not exceeding 20 cm in foundation trenches, plinth, sides of foundation etc. complete for all lift

Item number
2.25(a)
Analysis basis
Details of cost for 10 cum
Priced inputs
7
Derived rate
700.50 / cum

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 2.25(a) Excavating, supplying, stacking and filling of local earth (including royalty) by mechanical transport upto a lead of 5km also including ramming and watering of the earth in layers not exceeding 20 cm in foundation trenches, plinth, sides of foundation etc. complete for all lift — is derived from 7 priced inputs for 10 cum and works out to ₹700.50 per cum after water charges, GST, CPOH and cess. The full build-up is below.

  • Carriage of materials upto 5 km
CodeInputUnitQuantityRate (INR)Amount (INR)
0020Hydraulic Excavator (3D) with driver and fuel. (Cofficient from item No 2.6.1)Hydraulic Excavator (3D) with driver and fuelMachineryday0.087,850.00628.00
0128MateLabourday0.04816.0032.64
0114Beldar (1/2x0.89=0.45 day)BeldarLabourday0.45736.00331.20
0115CoolieLabourday1.208736.00889.09
0101BhistiLabourday0.18816.00146.88
Rate as per item No 1.1.2 of SH:1 carriage of materials including loading, unloading and stackingRate as per item 1.1.2Sub-analysiscum10326.683,266.80
0979Royalty for good earthMaterialcum1060.00600.00
TOTAL
5,894.61
Add 1 % Water charges on “W-A”
26.28
TOTAL
5,920.89
Add GST on “X-A” (multiplying factor 0.2127)
564.52
TOTAL
6,485.41
Add 15% CPOH on “Y-A”
482.79
TOTAL
6,968.20
Add Cess @ 1% on “Z-A”
37.01
Cost of 10 cum
7,005.21
Cost of 1 cum
700.52
Say
700.50

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 127. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works