Skip to main content
R/DAR 2023

Note for item no. 2.24:- The extra percentage rate is applicable in respect of each item but limited to quantities of work executed in these difficult conditions. The unit, namely, metre depth, to be considered for payment, shall be the depth measured from the sub soil water level up to the centre of gravity of the qty executed in difficult conditions. The depth shall be reckoned correct to 0.10 m, (0.05 m or more shall be taken as 0.10 m and less than 0.05 m ignored.) Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 and for all lift

Item number
2.25
Analysis basis
10 cum
Priced inputs
4
Derived rate
₹196.00/ CUM
D-01/RATE ANALYSISITEM 2.25

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 2.25 (Note for item no. 2.24:- The extra percentage rate is applicable in respect of each item but limited to quantities of work executed in these difficult conditions. The unit, namely, metre depth, to be considered for payment, shall be the depth measured from the sub soil water level up to the centre of gravity of the qty executed in difficult conditions. The depth shall be reckoned correct to 0.10 m, (0.05 m or more shall be taken as 0.10 m and less than 0.05 m ignored.) Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 and for all lift) is derived from 4 priced inputs for 10 cum and works out to ₹196.00 per cum after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 2.25DETAILS OF COST FOR 10 CUM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0114LABBeldarday0.45736.00331.20
0115LABCoolieday1.208736.00889.09
0101LABBhistiday0.18816.00146.88
9999MATSundries (Minor T&P)L.S.4.612.2710.46
BUILD-UP TO RATE
TOTAL
1,377.63
Add 1 % Water charges on “W”
+13.78
TOTAL
1,391.41
Add GST on “X” (multiplying factor 0.2127)
+295.95
TOTAL
1,687.36
Add 15% CPOH on “Y”
+253.10
TOTAL
1,940.46
Add Cess @ 1% on “Z”
+19.40
Cost of 10 cum.
1,959.86
Cost of 1 cum.
195.99
SAY
₹196.00
D-02/SOURCEPRINTED PAGE 127
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
127

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 127. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSEARTH WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.