Skip to main content

CPWD Analysis of Rates · Earth Work

Note for item no. 2.24:- The extra percentage rate is applicable in respect of each item but limited to quantities of work executed in these difficult conditions. The unit, namely, metre depth, to be considered for payment, shall be the depth measured from the sub soil water level up to the centre of gravity of the qty executed in difficult conditions. The depth shall be reckoned correct to 0.10 m, (0.05 m or more shall be taken as 0.10 m and less than 0.05 m ignored.) Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 and for all lift

Item number
2.25
Analysis basis
Details of cost for 10 cum.
Priced inputs
4
Derived rate
196.00 / cum

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 2.25 Note for item no. 2.24:- The extra percentage rate is applicable in respect of each item but limited to quantities of work executed in these difficult conditions. The unit, namely, metre depth, to be considered for payment, shall be the depth measured from the sub soil water level up to the centre of gravity of the qty executed in difficult conditions. The depth shall be reckoned correct to 0.10 m, (0.05 m or more shall be taken as 0.10 m and less than 0.05 m ignored.) Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 and for all lift — is derived from 4 priced inputs for 10 cum and works out to ₹196.00 per cum after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
0114BeldarLabourday0.45736.00331.20
0115CoolieLabourday1.208736.00889.09
0101BhistiLabourday0.18816.00146.88
9999Sundries (Minor T&P)MaterialL.S.4.612.2710.46
TOTAL
1,377.63
Add 1 % Water charges on “W”
13.78
TOTAL
1,391.41
Add GST on “X” (multiplying factor 0.2127)
295.95
TOTAL
1,687.36
Add 15% CPOH on “Y”
253.10
TOTAL
1,940.46
Add Cess @ 1% on “Z”
19.40
Cost of 10 cum.
1,959.86
Cost of 1 cum.
195.99
Say
196.00

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 127. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works