Surface dressing of the ground including removing vegetation and in-equalities not exceeding 15 cm deep and disposal of rubbish, lead up to 50 m and lift up to 1.5 m
- Item number
- 2.28.1
- Analysis basis
- 100 sqm
- Priced inputs
- 2
- Derived rate
- ₹34.15/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 2.28.1 (Surface dressing of the ground including removing vegetation and in-equalities not exceeding 15 cm deep and disposal of rubbish, lead up to 50 m and lift up to 1.5 m All kinds of soil) is derived from 2 priced inputs for 100 sqm and works out to ₹34.15 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0114 | LAB | Beldar | day | 1.97 | 736.00 | 1,449.92 |
| 0115 | LAB | Coolie | day | 1.29 | 736.00 | 949.44 |
- TOTAL
- 2,399.36
- Add 1 % Water charges on “W”
- +23.99
- TOTAL
- 2,423.35
- Add GST on “X” (multiplying factor 0.2127)
- +515.45
- TOTAL
- 2,938.80
- Add 15% CPOH on “Y”
- +440.82
- TOTAL
- 3,379.62
- Add Cess @ 1% on “Z”
- +33.80
- Cost of 100 sqm.
- 3,413.42
- Cost of 1 sqm.
- 34.13
- SAY
- ₹34.15
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 129
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 129. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.