CPWD Analysis of Rates · Earth Work
Surface dressing of the ground including removing vegetation and in-equalities not exceeding 15 cm deep and disposal of rubbish, lead up to 50 m and lift up to 1.5 m
All kinds of soil
- Item number
- 2.28.1
- Analysis basis
- Details of cost for 100 sqm.
- Priced inputs
- 2
- Derived rate
- ₹34.15 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 2.28.1 — Surface dressing of the ground including removing vegetation and in-equalities not exceeding 15 cm deep and disposal of rubbish, lead up to 50 m and lift up to 1.5 m All kinds of soil — is derived from 2 priced inputs for 100 sqm and works out to ₹34.15 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0114 | BeldarLabour | day | 1.97 | 736.00 | 1,449.92 |
| 0115 | CoolieLabour | day | 1.29 | 736.00 | 949.44 |
- TOTAL
- 2,399.36
- Add 1 % Water charges on “W”
- 23.99
- TOTAL
- 2,423.35
- Add GST on “X” (multiplying factor 0.2127)
- 515.45
- TOTAL
- 2,938.80
- Add 15% CPOH on “Y”
- 440.82
- TOTAL
- 3,379.62
- Add Cess @ 1% on “Z”
- 33.80
- Cost of 100 sqm.
- 3,413.42
- Cost of 1 sqm.
- 34.13
- Say
- 34.15
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 129. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.