Earth work by mechinical / manual means in rough excavation, banking excavated earth in layers not exceeding 20cm in depth, breaking clods, watering, rolling each layer with ½ tonne roller or wooden or steel rammers, and rolling every 3rd and top-most layer with power roller of minimum 8 tonnes and dressing up in embankments for roads, flood banks, marginal banks and guide banks or filling up ground depressions, lead upto 50 m and for all lift

All kinds of soil
Item number
2.2.1
Analysis basis
10 cum
Priced inputs
8
Derived rate
₹395.30/ CUM
D-01/RATE ANALYSISITEM 2.2.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 2.2.1 (Earth work by mechinical / manual means in rough excavation, banking excavated earth in layers not exceeding 20cm in depth, breaking clods, watering, rolling each layer with ½ tonne roller or wooden or steel rammers, and rolling every 3rd and top-most layer with power roller of minimum 8 tonnes and dressing up in embankments for roads, flood banks, marginal banks and guide banks or filling up ground depressions, lead upto 50 m and for all lift : All kinds of soil) is derived from 8 priced inputs for 10 cum and works out to ₹395.30 per cum after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 2.2.1DETAILS OF COST FOR 10 CUM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0051MACHHydraulic Excavator 1 cum bucket capacityHydraulic Excavator of 1 cum buckethour1.538900.001,384.20
0049MACHDozer 80 HP for spreadingDozer 80 HPhour0.3741,700.00635.80
0050MACHMotor grader for gradingMotor Grader 3.35 metre bladehour0.1672,700.00450.90
0054MACHVibratory roller 8-10 tonneVibratory roller 8 to 10 tonnehour0.167700.00116.90
0057MACHWater tanker 6 KL capacityWater Tanker 5 to 6 KL capacityhour0.4250.00100.00
0128LABMateday0.004816.003.26
0115LABCoolieday0.1736.0073.60
9999MATSundries (i.e. watch and ward, minor T&P etc.)L.S.6.182.2714.03
BUILD-UP TO RATE
TOTAL
2,778.69
Add 1 % Water charges on “W”
+27.79
TOTAL
2,806.48
Add GST on “X” (multiplying factor 0.2127)
+596.94
TOTAL
3,403.42
Add 15% CPOH on “Y”
+510.51
TOTAL
3,913.93
Add Cess @ 1% on “Z”
+39.14
Cost of 10 cum.
3,953.07
Cost of 1 cum.
395.31
SAY
₹395.30
D-02/SOURCEPRINTED PAGE 93
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
93

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 93. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSEARTH WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.