R/DAR 2023

Earth work in surface excavation not exceeding 30 cm in depth but exceeding 1.5 m in width as well as 10 sqm on plan including getting out and disposal of excavated earth upto 50 m and lift upto 1.5 m, as directed by Engineer-inCharge

All kinds of soil
Item number
2.1.1
Analysis basis
100 Sqm
Priced inputs
2
Derived rate
₹129.85/ SQM
D-01/RATE ANALYSISITEM 2.1.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 2.1.1 (Earth work in surface excavation not exceeding 30 cm in depth but exceeding 1.5 m in width as well as 10 sqm on plan including getting out and disposal of excavated earth upto 50 m and lift upto 1.5 m, as directed by Engineer-inCharge: All kinds of soil) is derived from 2 priced inputs for 100 Sqm and works out to ₹129.85 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 2.1.1DETAILS OF COST FOR 100 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0114LABBeldarday6.8736.005,004.80
0115LABCoolieday5.6736.004,121.60
BUILD-UP TO RATE
TOTAL
9,126.40
Add 1 % Water charges on “W”
+91.26
TOTAL
9,217.66
Add GST on “X” (multiplying factor 0.2127)
+1,960.60
TOTAL
11,178.26
Add 15% CPOH on “Y”
+1,676.74
TOTAL
12,855.00
Add Cess @ 1% on “Z”
+128.55
Cost of 100 sqm
12,983.55
Cost of 1 sqm
129.84
SAY
₹129.85
D-02/SOURCEPRINTED PAGE 93
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
93

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 93. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSEARTH WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.