CPWD Analysis of Rates · Earth Work
Earth work in surface excavation not exceeding 30 cm in depth but exceeding 1.5 m in width as well as 10 sqm on plan including getting out and disposal of excavated earth upto 50 m and lift upto 1.5 m, as directed by Engineer-inCharge
All kinds of soil
- Item number
- 2.1.1
- Analysis basis
- Details of cost for 100 Sqm
- Priced inputs
- 2
- Derived rate
- ₹129.85 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 2.1.1 — Earth work in surface excavation not exceeding 30 cm in depth but exceeding 1.5 m in width as well as 10 sqm on plan including getting out and disposal of excavated earth upto 50 m and lift upto 1.5 m, as directed by Engineer-inCharge: All kinds of soil — is derived from 2 priced inputs for 100 Sqm and works out to ₹129.85 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0114 | BeldarLabour | day | 6.8 | 736.00 | 5,004.80 |
| 0115 | CoolieLabour | day | 5.6 | 736.00 | 4,121.60 |
- TOTAL
- 9,126.40
- Add 1 % Water charges on “W”
- 91.26
- TOTAL
- 9,217.66
- Add GST on “X” (multiplying factor 0.2127)
- 1,960.60
- TOTAL
- 11,178.26
- Add 15% CPOH on “Y”
- 1,676.74
- TOTAL
- 12,855.00
- Add Cess @ 1% on “Z”
- 128.55
- Cost of 100 sqm
- 12,983.55
- Cost of 1 sqm
- 129.84
- Say
- 129.85
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 93. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.