Skip to main content

CPWD Analysis of Rates · Earth Work

Earth work in surface excavation not exceeding 30 cm in depth but exceeding 1.5 m in width as well as 10 sqm on plan including getting out and disposal of excavated earth upto 50 m and lift upto 1.5 m, as directed by Engineer-inCharge

All kinds of soil

Item number
2.1.1
Analysis basis
Details of cost for 100 Sqm
Priced inputs
2
Derived rate
129.85 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 2.1.1 Earth work in surface excavation not exceeding 30 cm in depth but exceeding 1.5 m in width as well as 10 sqm on plan including getting out and disposal of excavated earth upto 50 m and lift upto 1.5 m, as directed by Engineer-inCharge: All kinds of soil — is derived from 2 priced inputs for 100 Sqm and works out to ₹129.85 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
0114BeldarLabourday6.8736.005,004.80
0115CoolieLabourday5.6736.004,121.60
TOTAL
9,126.40
Add 1 % Water charges on “W”
91.26
TOTAL
9,217.66
Add GST on “X” (multiplying factor 0.2127)
1,960.60
TOTAL
11,178.26
Add 15% CPOH on “Y”
1,676.74
TOTAL
12,855.00
Add Cess @ 1% on “Z”
128.55
Cost of 100 sqm
12,983.55
Cost of 1 sqm
129.84
Say
129.85

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 93. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works