CPWD Analysis of Rates · Earth Work

Excavating trenches of required width for pipes, cables, etc, including excavation for sockets, depth upto 1.5 m, including getting out the excavated materials, returning the soil as required in layers not exceeding 20 cm in depth, including consolidating each deposited layers by ramming, watering etc., stacking serviceable material for measurements and disposal of unserviceable material as directed, within a lead of 50 m : Hard rock (requiring blasting)

Pipes, cables etc. exceeding 80 mm dia but not exceeding 300 mm dia

Item number
2.13.2.2
Analysis basis
Details of cost for 80 m length of a pipe of an
Priced inputs
3
Derived rate
1,493.60 / m

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 2.13.2.2 Excavating trenches of required width for pipes, cables, etc, including excavation for sockets, depth upto 1.5 m, including getting out the excavated materials, returning the soil as required in layers not exceeding 20 cm in depth, including consolidating each deposited layers by ramming, watering etc., stacking serviceable material for measurements and disposal of unserviceable material as directed, within a lead of 50 m : Hard rock (requiring blasting) Pipes, cables etc. exceeding 80 mm dia but not exceeding 300 mm dia — is derived from 3 priced inputs for 80 m and works out to ₹1,493.60 per m after water charges, GST, CPOH and cess. The full build-up is below.

  • average dia. say 200mm.
  • Slope assumed 1:200
  • ExcavationQuantity same as in item No.2.13.1.2
  • Refilling, ramming and watering
  • Extra labour for ramming of rock
CodeInputUnitQuantityRate (INR)Amount (INR)
Rate as per item No. 2.9.2 of SH: Earth WorkRate as per item 2.9.2Sub-analysiscum93.61,049.8098,261.28
Rate as per item No.2.25 of SH: Earth WorkRate as per item 2.25Sub-analysiscum93.6196.0018,345.60
0114BeldarLabourday2.75736.002,024.00
TOTAL
1,18,630.88
Add 1 % Water charges on “W-A”
20.24
TOTAL
1,18,651.12
Add GST on “X-A” (multiplying factor 0.2127)
434.81
TOTAL
1,19,085.93
Add 15% CPOH on “Y-A”
371.86
TOTAL
1,19,457.79
Add Cess @ 1% on “Z-A”
28.51
Cost for 80 m. length of pipe
1,19,486.30
Cost for 1m. length of pipe
1,493.58
Say
1,493.60

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 103. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.