Excavating trenches of required width for pipes, cables, etc, including excavation for sockets, depth upto 1.5 m, including getting out the excavated materials, returning the soil as required in layers not exceeding 20 cm in depth, including consolidating each deposited layers by ramming, watering etc., stacking serviceable material for measurements and disposal of unserviceable material as directed, within a lead of 50 m : Hard rock (requiring blasting)

Pipes, cables etc. exceeding 300 mm dia but not exceeding 600 mm dia
Item number
2.13.2.3
Analysis basis
30 m
Priced inputs
3
Derived rate
₹1,718.45/ M
D-01/RATE ANALYSISITEM 2.13.2.3

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 2.13.2.3 (Excavating trenches of required width for pipes, cables, etc, including excavation for sockets, depth upto 1.5 m, including getting out the excavated materials, returning the soil as required in layers not exceeding 20 cm in depth, including consolidating each deposited layers by ramming, watering etc., stacking serviceable material for measurements and disposal of unserviceable material as directed, within a lead of 50 m : Hard rock (requiring blasting) Pipes, cables etc. exceeding 300 mm dia but not exceeding 600 mm dia) is derived from 3 priced inputs for 30 m and works out to ₹1,718.45 per m after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • average dia. Say 450mm.
  • Slope assumed 1:200
  • ExcavationQuantity same as in item No.2.13.1.3
  • Refilling, ramming and watering
  • Extra labour for ramming of rock
ANALYSIS OF RATES · ITEM 2.13.2.3DETAILS OF COST FOR 30 M LENGTH OF A PIPE OF AN
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per item No. 2.9.2 of SH: Earth WorkRate as per item 2.9.2cum40.3991,049.8042,410.87
SUBRate as per item No.2.25 of SH: Earth WorkRate as per item 2.25cum40.399196.007,918.20
0114LABBeldarday1.17736.00861.12
BUILD-UP TO RATE
TOTAL
51,190.19
Add 1 % Water charges on “W-A”
+8.61
TOTAL
51,198.80
Add GST on “X-A” (multiplying factor 0.2127)
+184.99
TOTAL
51,383.79
Add 15% CPOH on “Y-A”
+158.21
TOTAL
51,542.00
Add Cess @ 1% on “Z-A”
+12.13
Cost for 30 m. length of pipe
51,554.13
Cost for 1m. length of pipe
1,718.47
SAY
₹1,718.45
D-02/SOURCEPRINTED PAGE 103
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
103

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 103. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.