Skip to main content

CPWD Analysis of Rates · Earth Work

Excavating trenches of required width for pipes, cables, etc, including excavation for sockets, depth upto 1.5 m, including getting out the excavated materials, returning the soil as required in layers not exceeding 20 cm in depth, including consolidating each deposited layers by ramming, watering etc., stacking serviceable material for measurements and disposal of unserviceable material as directed, within a lead of 50 m : Hard rock (requiring blasting)

Pipes, cables etc. not exceeding 80 mm dia

Item number
2.13.2.1
Analysis basis
Details of cost for 180 m length of a pipe of a
Priced inputs
3
Derived rate
603.20 / m

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 2.13.2.1 Excavating trenches of required width for pipes, cables, etc, including excavation for sockets, depth upto 1.5 m, including getting out the excavated materials, returning the soil as required in layers not exceeding 20 cm in depth, including consolidating each deposited layers by ramming, watering etc., stacking serviceable material for measurements and disposal of unserviceable material as directed, within a lead of 50 m : Hard rock (requiring blasting) Pipes, cables etc. not exceeding 80 mm dia — is derived from 3 priced inputs for 180 m and works out to ₹603.20 per m after water charges, GST, CPOH and cess. The full build-up is below.

  • average dia. say 40mm.
  • Slope assumed 1:200
  • ExcavationQuantity same as in item No.2.10.1.1
  • Refilling, ramming and watering
  • Extra labour for ramming of rock
CodeInputUnitQuantityRate (INR)Amount (INR)
Rate as per item no. 2.9.2 of SH: Earth WorkRate as per item 2.9.2Sub-analysiscum85.051,049.8089,285.49
Rate as per item No.2.25 of SH: Earth WorkRate as per item 2.25Sub-analysiscum85.05196.0016,669.80
0114BeldarLabourday2.5736.001,840.00
TOTAL
1,07,795.29
Add 1 % Water charges on “W-A”
18.40
TOTAL
1,07,813.69
Add GST on “X-A” (multiplying factor 0.2127)
395.28
TOTAL
1,08,208.97
Add 15% CPOH on “Y-A”
338.05
TOTAL
1,08,547.02
Add Cess @ 1% on “Z-A”
25.92
Cost for 180 m. length of pipe
1,08,572.94
Cost for 1m. length of pipe
603.18
Say
603.20

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 102. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works