Excavating trenches of required width for pipes, cables, etc, including excavation for sockets, depth upto 1.5 m, including getting out the excavated materials, returning the soil as required in layers not exceeding 20 cm in depth, including consolidating each deposited layers by ramming, watering etc., stacking serviceable material for measurements and disposal of unserviceable material as directed, within a lead of 50 m : Ordinary rock
- Item number
- 2.13.1.3
- Analysis basis
- 30 m
- Priced inputs
- 3
- Derived rate
- ₹1,149.10/ M
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 2.13.1.3 (Excavating trenches of required width for pipes, cables, etc, including excavation for sockets, depth upto 1.5 m, including getting out the excavated materials, returning the soil as required in layers not exceeding 20 cm in depth, including consolidating each deposited layers by ramming, watering etc., stacking serviceable material for measurements and disposal of unserviceable material as directed, within a lead of 50 m : Ordinary rock : Pipes, cables exceeding 300 mm dia but not exceeding 600 mm dia) is derived from 3 priced inputs for 30 m and works out to ₹1,149.10 per m after water charges, GST, CPOH and cess. The full build-up is below.
- an average dia. say 450mm.
- Slope assumed 1 in 200.
- ExcavationMinimum depth of trench.
- 0.75+0.15+0.45 = 1.35m
- Average depth = (1.35+1.50)/2 = 1.425m
- Minimum width of trench = 0.90m
- 30x0.90x1.425 = 38.475 cum.
- 5% for collar = 1.924cum
- Total = 40.399cum
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| SUB | Rate as per item No. 2.9.1 of SH: Earth WorkRate as per item 2.9.1 | cum | 40.399 | 632.95 | 25,570.55 | |
| SUB | Rate as per item No.2.25 of SH: Earth WorkRate as per item 2.25 | cum | 40.399 | 196.00 | 7,918.20 | |
| 0114 | LAB | Beldar | day | 0.94 | 736.00 | 691.84 |
- TOTAL
- 34,180.59
- Add 1 % Water charges on “W-A”
- +6.92
- TOTAL
- 34,187.51
- Add GST on “X-A” (multiplying factor 0.2127)
- +148.63
- TOTAL
- 34,336.14
- Add 15% CPOH on “Y-A”
- +127.11
- TOTAL
- 34,463.25
- Add Cess @ 1% on “Z-A”
- +9.74
- Cost for 30 m length of a pipe
- 34,472.99
- Cost for one m length of a pipe
- 1,149.10
- SAY
- ₹1,149.10
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 102
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 102. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.