Excavating trenches of required width for pipes, cables, etc, including excavation for sockets, depth upto 1.5 m, including getting out the excavated materials, returning the soil as required in layers not exceeding 20 cm in depth, including consolidating each deposited layers by ramming, watering etc., stacking serviceable material for measurements and disposal of unserviceable material as directed, within a lead of 50 m : Ordinary rock

Pipes, cables etc. exceeding 80 mm dia but not exceeding 300 mm dia

Item number
2.13.1.2
Analysis basis
Details of cost for 80 m length of pipe of an
Priced inputs
3
Derived rate
998.65 / m

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 2.13.1.2 Excavating trenches of required width for pipes, cables, etc, including excavation for sockets, depth upto 1.5 m, including getting out the excavated materials, returning the soil as required in layers not exceeding 20 cm in depth, including consolidating each deposited layers by ramming, watering etc., stacking serviceable material for measurements and disposal of unserviceable material as directed, within a lead of 50 m : Ordinary rock : Pipes, cables etc. exceeding 80 mm dia but not exceeding 300 mm dia — is derived from 3 priced inputs for 80 m and works out to ₹998.65 per m after water charges, GST, CPOH and cess. The full build-up is below.

  • average dia. Say 200mm.
  • Slope assumed 1:200
  • ExcavationMinimum depth of trench.
  • 0.75+0.15+0.20 = 1.10m
  • Average depth = (1.10+1.50)/2 = 1.30m
  • Minimum width of trench = 0.90m
  • 80x0.90x1.30 = 93.60 cum.
  • Refilling, ramming and watering
  • Extra labour for ramming of rock
CodeInputUnitQuantityRate (INR)Amount (INR)
Rate as per item No. 2.9.1 of SH: Earth WorkRate as per item 2.9.1Sub-analysiscum93.6632.9559,244.12
Rate as per item No.2.25 of SH: Earth WorkRate as per item 2.25Sub-analysiscum93.6196.0018,345.60
0114BeldarLabourday2.2736.001,619.20
TOTAL
79,208.92
Add 1 % Water charges on “W-A”
16.19
TOTAL
79,225.11
Add GST on “X-A” (multiplying factor 0.2127)
347.85
TOTAL
79,572.96
Add 15% CPOH on “Y-A”
297.49
TOTAL
79,870.45
Add Cess @ 1% on “Z-A”
22.81
Cost for 80 m. length of pipe
79,893.26
Cost for 1m. length of pipe
998.67
Say
998.65

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 101. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.