Excavating trenches of required width for pipes, cables, etc, including excavation for sockets, depth upto 1.5 m, including getting out the excavated materials, returning the soil as required in layers not exceeding 20 cm in depth, including consolidating each deposited layers by ramming, watering etc., stacking serviceable material for measurements and disposal of unserviceable material as directed, within a lead of 50 m : Ordinary rock

Pipes, cables etc. exceeding 80 mm dia but not exceeding 300 mm dia
Item number
2.13.1.2
Analysis basis
80 m
Priced inputs
3
Derived rate
₹998.65/ M
D-01/RATE ANALYSISITEM 2.13.1.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 2.13.1.2 (Excavating trenches of required width for pipes, cables, etc, including excavation for sockets, depth upto 1.5 m, including getting out the excavated materials, returning the soil as required in layers not exceeding 20 cm in depth, including consolidating each deposited layers by ramming, watering etc., stacking serviceable material for measurements and disposal of unserviceable material as directed, within a lead of 50 m : Ordinary rock : Pipes, cables etc. exceeding 80 mm dia but not exceeding 300 mm dia) is derived from 3 priced inputs for 80 m and works out to ₹998.65 per m after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • average dia. Say 200mm.
  • Slope assumed 1:200
  • ExcavationMinimum depth of trench.
  • 0.75+0.15+0.20 = 1.10m
  • Average depth = (1.10+1.50)/2 = 1.30m
  • Minimum width of trench = 0.90m
  • 80x0.90x1.30 = 93.60 cum.
  • Refilling, ramming and watering
  • Extra labour for ramming of rock
ANALYSIS OF RATES · ITEM 2.13.1.2DETAILS OF COST FOR 80 M LENGTH OF PIPE OF AN
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per item No. 2.9.1 of SH: Earth WorkRate as per item 2.9.1cum93.6632.9559,244.12
SUBRate as per item No.2.25 of SH: Earth WorkRate as per item 2.25cum93.6196.0018,345.60
0114LABBeldarday2.2736.001,619.20
BUILD-UP TO RATE
TOTAL
79,208.92
Add 1 % Water charges on “W-A”
+16.19
TOTAL
79,225.11
Add GST on “X-A” (multiplying factor 0.2127)
+347.85
TOTAL
79,572.96
Add 15% CPOH on “Y-A”
+297.49
TOTAL
79,870.45
Add Cess @ 1% on “Z-A”
+22.81
Cost for 80 m. length of pipe
79,893.26
Cost for 1m. length of pipe
998.67
SAY
₹998.65
D-02/SOURCEPRINTED PAGE 101
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
101

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 101. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSEARTH WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.