Excavating trenches of required width for pipes, cables, etc, including excavation for sockets, depth upto 1.5 m, including getting out the excavated materials, returning the soil as required in layers not exceeding 20 cm in depth, including consolidating each deposited layers by ramming, watering etc., stacking serviceable material for measurements and disposal of unserviceable material as directed, within a lead of 50 m : Ordinary rock

Pipes, cables etc. not exceeding 80 mm dia
Item number
2.13.1.1
Analysis basis
180 m
Priced inputs
3
Derived rate
₹403.30/ M
D-01/RATE ANALYSISITEM 2.13.1.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 2.13.1.1 (Excavating trenches of required width for pipes, cables, etc, including excavation for sockets, depth upto 1.5 m, including getting out the excavated materials, returning the soil as required in layers not exceeding 20 cm in depth, including consolidating each deposited layers by ramming, watering etc., stacking serviceable material for measurements and disposal of unserviceable material as directed, within a lead of 50 m : Ordinary rock : Pipes, cables etc. not exceeding 80 mm dia) is derived from 3 priced inputs for 180 m and works out to ₹403.30 per m after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • a average dia. say 40mm.
  • Slope assumed 1:200
  • ExcavationQuantity same as in item No.2.10.1.1
  • Refilling, ramming and watering
  • Extra labour for ramming of rock
ANALYSIS OF RATES · ITEM 2.13.1.1DETAILS OF COST FOR 180 M LENGTH OF A PIPE OF
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per Item No. 2.9.1 of SH: Earth WorkRate as per item 2.9.1cum85.05632.9553,832.40
SUBRate as per item No.2.25 of SH: Earth WorkRate as per item 2.25cum85.05196.0016,669.80
0114LABBeldarday2736.001,472.00
BUILD-UP TO RATE
TOTAL
71,974.20
Add 1 % Water charges on “W-A”
+14.72
TOTAL
71,988.92
Add GST on “X-A” (multiplying factor 0.2127)
+316.23
TOTAL
72,305.15
Add 15% CPOH on “Y-A”
+270.44
TOTAL
72,575.59
Add Cess @ 1% on “Z-A”
+20.73
Cost for 180 m. length of pipe
72,596.32
Cost for 1m. length of pipe
403.31
SAY
₹403.30
D-02/SOURCEPRINTED PAGE 100
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
100

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 100. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSEARTH WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.