Excavating trenches by mechinical / manual means of required width for pipes, cables, etc including excavation for sockets, and dressing of sides, ramming of bottoms, for all depth, including getting out the excavated soil, and then returning the soil as required, in layers not exceeding 20 cm in depth, including consolidating each deposited layer by ramming, watering, etc. and disposing of surplus excavated soil as directed, within a lead of 50 m : All kinds of soil

Pipes, cables etc. exceeding 300 mm dia but not exceeding 600 mm
Item number
2.10.1.3
Analysis basis
60m length
Priced inputs
2
Derived rate
₹549.75/ M LENGTH
D-01/RATE ANALYSISITEM 2.10.1.3

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 2.10.1.3 (Excavating trenches by mechinical / manual means of required width for pipes, cables, etc including excavation for sockets, and dressing of sides, ramming of bottoms, for all depth, including getting out the excavated soil, and then returning the soil as required, in layers not exceeding 20 cm in depth, including consolidating each deposited layer by ramming, watering, etc. and disposing of surplus excavated soil as directed, within a lead of 50 m : All kinds of soil Pipes, cables etc. exceeding 300 mm dia but not exceeding 600 mm) is derived from 2 priced inputs for 60m length and works out to ₹549.75 per m length after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • average dia. say 450mm. Slope assumed 1
  • in 200.
  • Earth work and filling- Minimum depth of
  • trench 0.75+0.45= 1.20m, Average depth =
  • (1.50+1.20)/2 = 1.35, Width = 0.40 + 0.45 =
  • 0.85 m, 60x0.85x1.35 = 68.85 cum, 5% for
  • collars = 3.44 cum, Total = 72.29 cum
ANALYSIS OF RATES · ITEM 2.10.1.3DETAILS OF COST FOR 60M LENGTH OF A PIPE OF AN
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per item No. 2.8.1 of SH: Earth workRate as per item 2.8.1cum72.29260.3018,817.09
SUBRate as per Item No. 2.25 of SH: Earth WorkRate as per item 2.25cum72.29196.0014,168.84
BUILD-UP TO RATE
TOTAL
32,985.93
Cost of 60m length of pipe
32,985.93
Cost for 1m length of pipe
549.77
SAY
₹549.75
D-02/SOURCEPRINTED PAGE 100
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
100

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 100. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSEARTH WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.