Providing and laying non-pressure NP2 class (light duty) R.C.C. pipes with collars jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete

800 mm dia. R.C.C. pipe

Item number
19.6.9
Analysis basis
Details of cost for 10 metre
Priced inputs
8
Derived rate
3,511.95 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.6.9 Providing and laying non-pressure NP2 class (light duty) R.C.C. pipes with collars jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete : 800 mm dia. R.C.C. pipe — is derived from 8 priced inputs for 10 metre and works out to ₹3,511.95 per metre after water charges, GST, CPOH and cess. The full build-up is below.

  • (in 2.5 m. length = 4 Nos.)
  • 4 Nos.
  • Cement of 4 joints = 4x0.0072 = 0.0288
  • cum = 0.042 tonne
  • Fine sand for 4 joints = 0.0143x4 =
  • 0.0572 cum = 0.057 cum
CodeInputUnitQuantityRate (INR)Amount (INR)
1709R.C.C. pipes NP2 class 800 mm diaMaterialmetre101,950.0019,500.00
1723R.C.C. collars NP2 class 800 mm diaMaterialeach4235.00940.00
0367Portland Cement (OPC-43 grade)Materialtonne0.0425,156.00216.55
0983Fine sand (zone IV)Materialcum0.057980.0055.86
0123Mason 1st classMason 1st classLabourday1.14897.001,022.58
0124Mason 2nd classMason 2nd classLabourday1.14816.00930.24
0114BeldarLabourday2.28736.001,678.08
0101BhistiLabourday0.42816.00342.72
TOTAL
24,686.03
Add 1 % Water charges on “W”
246.86
TOTAL
24,932.89
Add GST on “X” (multiplying factor 0.2127)
5,303.23
TOTAL
30,236.12
Add 15% CPOH on “Y”
4,535.42
TOTAL
34,771.54
Add Cess @ 1% on “Z”
347.72
Cost of 10 metre
35,119.26
Cost of1 metre
3,511.93
Say
3,511.95

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1712. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.