Providing and laying non-pressure NP2 class (light duty) R.C.C. pipes with collars jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete

900 mm dia. R.C.C. pipe
Item number
19.6.10
Analysis basis
10 metre
Priced inputs
8
Derived rate
₹4,750.85/ METRE
D-01/RATE ANALYSISITEM 19.6.10

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.6.10 (Providing and laying non-pressure NP2 class (light duty) R.C.C. pipes with collars jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete : 900 mm dia. R.C.C. pipe) is derived from 8 priced inputs for 10 metre and works out to ₹4,750.85 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • (in 2.5 m. length = 4 Nos.)
  • 4 Nos.
  • Cement of 4 joints = 4x0.0082 = 0.0328
  • cum = 0.0488 t Say 0.049
  • Fine sand for 4 joints = 0.0164x4 = 0.066 cum
ANALYSIS OF RATES · ITEM 19.6.10DETAILS OF COST FOR 10 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1710MATR.C.C. pipes NP2 class 900 mm diametre102,728.0027,280.00
1724MATR.C.C. collars NP2 class 900 mm diaeach4260.001,040.00
0367MATPortland Cement (OPC-43 grade)tonne0.0495,156.00252.64
0983MATFine sand (zone IV)cum0.066980.0064.68
0123LABMason 1st classMason 1st classday1.25897.001,121.25
0124LABMason 2nd classMason 2nd classday1.25816.001,020.00
0114LABBeldarday3736.002,208.00
0101LABBhistiday0.5816.00408.00
BUILD-UP TO RATE
TOTAL
33,394.57
Add 1 % Water charges on “W”
+333.95
TOTAL
33,728.52
Add GST on “X” (multiplying factor 0.2127)
+7,174.06
TOTAL
40,902.58
Add 15% CPOH on “Y”
+6,135.39
TOTAL
47,037.97
Add Cess @ 1% on “Z”
+470.38
Cost of 10 metre
47,508.35
Cost of 1 metre
4,750.84
SAY
₹4,750.85
D-02/SOURCEPRINTED PAGE 1712
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1712

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1712. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSDRAINAGE
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.