Providing and laying non-pressure NP2 class (light duty) R.C.C. pipes with collars jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete

1000 mm dia. R.C.C. pipe
Item number
19.6.11
Analysis basis
10 metre
Priced inputs
8
Derived rate
₹5,562.60/ METRE
D-01/RATE ANALYSISITEM 19.6.11

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.6.11 (Providing and laying non-pressure NP2 class (light duty) R.C.C. pipes with collars jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete : 1000 mm dia. R.C.C. pipe) is derived from 8 priced inputs for 10 metre and works out to ₹5,562.60 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • (in 2.5 m. length = 4 Nos.)
  • 4 Nos.
  • Cement of 4 joints = 4x0.0092 = 0.0368
  • cum = 0.055 tonne
  • Cement of 4 joints = 4x0.0092 = 0.0368
  • cum = 0.055 tonne
  • Fine sand for 4 joints = 0.0185x4 = 0.074
  • cum
ANALYSIS OF RATES · ITEM 19.6.11DETAILS OF COST FOR 10 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1711MATR.C.C. pipes NP2 class 1000 mm diametre103,158.0031,580.00
1725MATR.C.C. collars NP2 class 1000 mm diaeach4310.001,240.00
0367MATPortland Cement (OPC-43 grade)tonne0.0555,156.00283.58
0983MATFine sand (zone IV)cum0.074980.0072.52
0123LABMason 1st classMason 1st classday1.36897.001,219.92
0124LABMason 2nd classMason 2nd classday1.36816.001,109.76
0114LABBeldarday4.33736.003,186.88
0101LABBhistiday0.5816.00408.00
BUILD-UP TO RATE
TOTAL
39,100.66
Add 1 % Water charges on “W”
+391.01
TOTAL
39,491.67
Add GST on “X” (multiplying factor 0.2127)
+8,399.88
TOTAL
47,891.55
Add 15% CPOH on “Y”
+7,183.73
TOTAL
55,075.28
Add Cess @ 1% on “Z”
+550.75
Cost of 10 metre
55,626.03
Cost of 1 metre
5,562.60
SAY
₹5,562.60
D-02/SOURCEPRINTED PAGE 1713
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1713

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1713. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.