CPWD Analysis of Rates · Drainage

Providing and laying non-pressure NP2 class (light duty) R.C.C. pipes with collars jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete

1100 mm dia. R.C.C. pipe

Item number
19.6.12
Analysis basis
Details of cost for 10 metre
Priced inputs
8
Derived rate
6,276.60 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.6.12 Providing and laying non-pressure NP2 class (light duty) R.C.C. pipes with collars jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete : 1100 mm dia. R.C.C. pipe — is derived from 8 priced inputs for 10 metre and works out to ₹6,276.60 per metre after water charges, GST, CPOH and cess. The full build-up is below.

  • (in 2.5 m. length = 4 Nos.)
  • 4 Nos.
  • Cement of 4 joints = 4x0.0103 =0.0412
  • cum = 0.061 tonne
  • Fine sand for 4 joints = 0.0206x4 =
  • 0.0824 cum = 0.082 cum
CodeInputUnitQuantityRate (INR)Amount (INR)
1712R.C.C. pipes NP2 class 1100 mm diaMaterialmetre103,478.0034,780.00
1726R.C.C. collars NP2 class 1100 mm diaMaterialeach4325.001,300.00
0367Portland Cement (OPC-43 grade)Materialtonne0.0615,156.00314.52
0983Fine sand (zone IV)Materialcum0.082980.0080.36
0123Mason 1st classMason 1st classLabourday1.47897.001,318.59
0124Mason 2nd classMason 2nd classLabourday1.47816.001,199.52
0114BeldarLabourday6.3736.004,636.80
0101BhistiLabourday0.6816.00489.60
TOTAL
44,119.39
Add 1 % Water charges on “W”
441.19
TOTAL
44,560.58
Add GST on “X” (multiplying factor 0.2127)
9,478.04
TOTAL
54,038.62
Add 15% CPOH on “Y”
8,105.79
TOTAL
62,144.41
Add Cess @ 1% on “Z”
621.44
Cost of 10 metre
62,765.85
Cost of 1 metre
6,276.59
Say
6,276.60

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1713. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.