Providing and laying non-pressure NP2 class (light duty) R.C.C. pipes with collars jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete

1200 mm dia. R.C.C. pipe

Item number
19.6.13
Analysis basis
Details of cost for 10 metre
Priced inputs
8
Derived rate
7,102.15 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.6.13 Providing and laying non-pressure NP2 class (light duty) R.C.C. pipes with collars jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete : 1200 mm dia. R.C.C. pipe — is derived from 8 priced inputs for 10 metre and works out to ₹7,102.15 per metre after water charges, GST, CPOH and cess. The full build-up is below.

  • (in 2.5 m. length = 4 Nos.)
  • 4 Nos.
  • Cement of 4 joints = 4x0.0114 = 0.0456
  • cum = 0.068 tonne
  • Fine sand for 4 joints = 0.0229x4 =
  • 0.0916 cum = 0.092 cum
CodeInputUnitQuantityRate (INR)Amount (INR)
1713R.C.C. pipes NP2 class 1200 mm diaMaterialmetre103,825.0038,250.00
1727R.C.C. collars NP2 class 1200 mm diaMaterialeach4395.001,580.00
0367Portland Cement (OPC-43 grade)Materialtonne0.0685,156.00350.61
0983Fine sand (zone IV)Materialcum0.092980.0090.16
0123Mason 1st classMason 1st classLabourday1.59897.001,426.23
0124Mason 2nd classMason 2nd classLabourday1.59816.001,297.44
0114BeldarLabourday8.67736.006,381.12
0101BhistiLabourday0.67816.00546.72
TOTAL
49,922.28
Add 1 % Water charges on “W”
499.22
TOTAL
50,421.50
Add GST on “X” (multiplying factor 0.2127)
10,724.65
TOTAL
61,146.15
Add 15% CPOH on “Y”
9,171.92
TOTAL
70,318.07
Add Cess @ 1% on “Z”
703.18
Cost of 10 metre
71,021.25
Cost of 1 metre
7,102.13
Say
7,102.15

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1714. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.