Providing and laying non-pressure NP2 class (light duty) R.C.C. pipes with collars jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete

600 mm dia. R.C.C. pipe
Item number
19.6.7
Analysis basis
10 metre
Priced inputs
8
Derived rate
₹2,243.40/ METRE
D-01/RATE ANALYSISITEM 19.6.7

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.6.7 (Providing and laying non-pressure NP2 class (light duty) R.C.C. pipes with collars jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete : 600 mm dia. R.C.C. pipe) is derived from 8 priced inputs for 10 metre and works out to ₹2,243.40 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Cement of 4 joints = 4x0.0054 = 0.0216
  • cum = 0.032 tonne
  • Fine sand for 4 joints = 0.0108x4 = 0.043
  • cum
ANALYSIS OF RATES · ITEM 19.6.7DETAILS OF COST FOR 10 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1706MATR.C.C. pipes NP2 class 600 mm dia (in 2.5 m. length = 4 Nos.)R.C.C. pipes NP2 class 600 mm diametre101,175.0011,750.00
1720MATR.C.C. collars NP2 class 600 mm dia 4 Nos.R.C.C. collars NP2 class 600 mm diaeach4155.00620.00
0367MATPortland Cement (OPC-43 grade)tonne0.0325,156.00164.99
0983MATFine sand (zone IV)cum0.043980.0042.14
0123LABMason 1st classMason 1st classday0.92897.00825.24
0124LABMason 2nd classMason 2nd classday0.92816.00750.72
0114LABBeldarday1.83736.001,346.88
0101LABBhistiday0.33816.00269.28
BUILD-UP TO RATE
TOTAL
15,769.25
Add 1 % Water charges on “W”
+157.69
TOTAL
15,926.94
Add GST on “X” (multiplying factor 0.2127)
+3,387.66
TOTAL
19,314.60
Add 15% CPOH on “Y”
+2,897.19
TOTAL
22,211.79
Add Cess @ 1% on “Z”
+222.12
Cost of 10 metre
22,433.91
Cost of 1 metre
2,243.39
SAY
₹2,243.40
D-02/SOURCEPRINTED PAGE 1711
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1711

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1711. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSDRAINAGE
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.