Providing and laying non-pressure NP2 class (light duty) R.C.C. pipes with collars jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete

500 mm dia. R.C.C. pipe

Item number
19.6.6
Analysis basis
Details of cost for 10 metre
Priced inputs
8
Derived rate
1,918.90 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.6.6 Providing and laying non-pressure NP2 class (light duty) R.C.C. pipes with collars jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete : 500 mm dia. R.C.C. pipe — is derived from 8 priced inputs for 10 metre and works out to ₹1,918.90 per metre after water charges, GST, CPOH and cess. The full build-up is below.

  • (in 2.5 m. length = 4 Nos.)
  • 4 Nos.
  • Cement of 4 joints = 4x0.0045 = 0.018
  • cum = 0.026 tonne
  • Fine sand for 4 joints = 0.0089x4 =
  • 0.0356 cum = 0.036 cum
CodeInputUnitQuantityRate (INR)Amount (INR)
1705R.C.C. pipes NP2 class 500 mm diaMaterialmetre10995.009,950.00
1719R.C.C. collars NP2 class 500 mm diaMaterialeach4130.00520.00
0367Portland Cement (OPC-43 grade)Materialtonne0.0265,156.00134.06
0983Fine sand (zone IV)Materialcum0.036980.0035.28
0123Mason 1st classMason 1st classLabourday0.81897.00726.57
0124Mason 2nd classMason 2nd classLabourday0.81816.00660.96
0114BeldarLabourday1.62736.001,192.32
0101BhistiLabourday0.33816.00269.28
TOTAL
13,488.47
Add 1 % Water charges on “W”
134.88
TOTAL
13,623.35
Add GST on “X” (multiplying factor 0.2127)
2,897.69
TOTAL
16,521.04
Add 15% CPOH on “Y”
2,478.16
TOTAL
18,999.20
Add Cess @ 1% on “Z”
189.99
Cost of 10 metre
19,189.19
Cost of 1 metre
1,918.92
Say
1,918.90

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1710. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.