R/DAR 2023

Providing and laying non-pressure NP2 class (light duty) R.C.C. pipes with collars jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete

450 mm dia. R.C.C. pipe
Item number
19.6.5
Analysis basis
10 metre
Priced inputs
8
Derived rate
₹1,620.95/ METRE
D-01/RATE ANALYSISITEM 19.6.5

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.6.5 (Providing and laying non-pressure NP2 class (light duty) R.C.C. pipes with collars jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete : 450 mm dia. R.C.C. pipe) is derived from 8 priced inputs for 10 metre and works out to ₹1,620.95 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • (in 2.5 m. length = 4 Nos.)
  • 4 Nos.
  • Cement of 4 joints = 4x0.0041 = 0.0164
  • cum = 0.024 tonne
  • Fine sand for 4 joint = 0.0082x4 = 0.033
  • cum
ANALYSIS OF RATES · ITEM 19.6.5DETAILS OF COST FOR 10 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1704MATR.C.C. pipes NP2 class 450 mm diametre10810.008,100.00
1718MATR.C.C. collars NP2 class 450 mm diaeach4120.00480.00
0367MATPortland Cement (OPC-43 grade)tonne0.0245,156.00123.74
0983MATFine sand (zone IV)cum0.033980.0032.34
0123LABMason 1st classMason 1st classday0.75897.00672.75
0124LABMason 2nd classMason 2nd classday0.75816.00612.00
0114LABBeldarday1.5736.001,104.00
0101LABBhistiday0.33816.00269.28
BUILD-UP TO RATE
TOTAL
11,394.11
Add 1 % Water charges on “W”
+113.94
TOTAL
11,508.05
Add GST on “X” (multiplying factor 0.2127)
+2,447.76
TOTAL
13,955.81
Add 15% CPOH on “Y”
+2,093.37
TOTAL
16,049.18
Add Cess @ 1% on “Z”
+160.49
Cost of 10 metre
16,209.67
Cost of 1 metre
1,620.97
SAY
₹1,620.95
D-02/SOURCEPRINTED PAGE 1709
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1709

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1709. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.