Providing and laying non-pressure NP2 class (light duty) R.C.C. pipes with collars jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete

300 mm dia. R.C.C. pipe
Item number
19.6.4
Analysis basis
10 metre
Priced inputs
8
Derived rate
₹994.30/ METRE
D-01/RATE ANALYSISITEM 19.6.4

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.6.4 (Providing and laying non-pressure NP2 class (light duty) R.C.C. pipes with collars jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete : 300 mm dia. R.C.C. pipe) is derived from 8 priced inputs for 10 metre and works out to ₹994.30 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • (in 2.5 m. length = 4 Nos.)
  • 4 Nos.
  • Cement of 4 joints = 4x0.00185 = 0.0074
  • cum = 0.011 tonne
  • Fine sand for 4 joint = 0.0037x4 = 0.0148
  • say 0.015cum
ANALYSIS OF RATES · ITEM 19.6.4DETAILS OF COST FOR 10 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1703MATR.C.C. pipes NP2 class 300 mm diametre10465.004,650.00
1717MATR.C.C. collars NP2 class 300 mm diaeach460.00240.00
0367MATPortland Cement (OPC-43 grade)tonne0.0115,156.0056.72
0983MATFine sand (zone IV)cum0.015980.0014.70
0123LABMason 1st classMason 1st classday0.59897.00529.23
0124LABMason 2nd classMason 2nd classday0.59816.00481.44
0114LABBeldarday1.16736.00853.76
0101LABBhistiday0.2816.00163.20
BUILD-UP TO RATE
TOTAL
6,989.05
Add 1 % Water charges on “W”
+69.89
TOTAL
7,058.94
Add GST on “X” (multiplying factor 0.2127)
+1,501.44
TOTAL
8,560.38
Add 15% CPOH on “Y”
+1,284.06
TOTAL
9,844.44
Add Cess @ 1% on “Z”
+98.44
Cost of 10 metre
9,942.88
Cost of 1 metre
994.29
SAY
₹994.30
D-02/SOURCEPRINTED PAGE 1709
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1709

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1709. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSDRAINAGE
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.