Providing and laying non-pressure NP2 class (light duty) R.C.C. pipes with collars jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete

250 mm dia. R.C.C. pipe

Item number
19.6.3
Analysis basis
Details of cost for 10 metre
Priced inputs
8
Derived rate
899.80 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.6.3 Providing and laying non-pressure NP2 class (light duty) R.C.C. pipes with collars jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete : 250 mm dia. R.C.C. pipe — is derived from 8 priced inputs for 10 metre and works out to ₹899.80 per metre after water charges, GST, CPOH and cess. The full build-up is below.

  • (in 2 m. length = 5 Nos.)
  • 5 Nos.
  • Cement of 5 joints = 5x0.0012 = 0.006
  • cum = 0.009tonne
  • Fine sand for 5 joint = 0.0024x5 = 0.012
  • cum
CodeInputUnitQuantityRate (INR)Amount (INR)
1702R.C.C. pipes NP2 class 250 mm diaMaterialmetre10375.003,750.00
1716R.C.C. collars NP2 class 250 mm diaMaterialeach560.00300.00
0367Portland Cement (OPC-43 grade)Materialtonne0.0095,156.0046.40
0983Fine sand (zone IV)Materialcum0.012980.0011.76
0123Mason 1st classMason 1st classLabourday0.54897.00484.38
0124Mason 2nd classMason 2nd classLabourday0.54816.00440.64
0114BeldarLabourday1.5736.001,104.00
0101BhistiLabourday0.23816.00187.68
TOTAL
6,324.86
Add 1 % Water charges on “W”
63.25
TOTAL
6,388.11
Add GST on “X” (multiplying factor 0.2127)
1,358.75
TOTAL
7,746.86
Add 15% CPOH on “Y”
1,162.03
TOTAL
8,908.89
Add Cess @ 1% on “Z”
89.09
Cost of 10 metre
8,997.98
Cost of 1 metre
899.80
Say
899.80

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1708. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.