Skip to main content
R/DAR 2023

Providing and laying non-pressure NP2 class (light duty) R.C.C. pipes with collars jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete

250 mm dia. R.C.C. pipe
Item number
19.6.3
Analysis basis
10 metre
Priced inputs
8
Derived rate
₹899.80/ METRE
D-01/RATE ANALYSISITEM 19.6.3

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.6.3 (Providing and laying non-pressure NP2 class (light duty) R.C.C. pipes with collars jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete : 250 mm dia. R.C.C. pipe) is derived from 8 priced inputs for 10 metre and works out to ₹899.80 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • (in 2 m. length = 5 Nos.)
  • 5 Nos.
  • Cement of 5 joints = 5x0.0012 = 0.006
  • cum = 0.009tonne
  • Fine sand for 5 joint = 0.0024x5 = 0.012
  • cum
ANALYSIS OF RATES · ITEM 19.6.3DETAILS OF COST FOR 10 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1702MATR.C.C. pipes NP2 class 250 mm diametre10375.003,750.00
1716MATR.C.C. collars NP2 class 250 mm diaeach560.00300.00
0367MATPortland Cement (OPC-43 grade)tonne0.0095,156.0046.40
0983MATFine sand (zone IV)cum0.012980.0011.76
0123LABMason 1st classMason 1st classday0.54897.00484.38
0124LABMason 2nd classMason 2nd classday0.54816.00440.64
0114LABBeldarday1.5736.001,104.00
0101LABBhistiday0.23816.00187.68
BUILD-UP TO RATE
TOTAL
6,324.86
Add 1 % Water charges on “W”
+63.25
TOTAL
6,388.11
Add GST on “X” (multiplying factor 0.2127)
+1,358.75
TOTAL
7,746.86
Add 15% CPOH on “Y”
+1,162.03
TOTAL
8,908.89
Add Cess @ 1% on “Z”
+89.09
Cost of 10 metre
8,997.98
Cost of 1 metre
899.80
SAY
₹899.80
D-02/SOURCEPRINTED PAGE 1708
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1708

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1708. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSDRAINAGE
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.