Providing and laying non-pressure NP2 class (light duty) R.C.C. pipes with collars jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete
- Item number
- 19.6.2
- Analysis basis
- 10 metre
- Priced inputs
- 8
- Derived rate
- ₹556.45/ METRE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.6.2 (Providing and laying non-pressure NP2 class (light duty) R.C.C. pipes with collars jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete : 150 mm dia. R.C.C. pipe) is derived from 8 priced inputs for 10 metre and works out to ₹556.45 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- (in 2 m. length = 5 Nos.)
- 5 Nos.
- Cement of 5 joints = 5x0.0008 = 0.004
- cum = 0.006 tonne
- Fine sand for 5 joint = 0.0016x5 = 0.008 cum
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 1701 | MAT | R.C.C. pipes NP2 class 150 mm dia | metre | 10 | 230.00 | 2,300.00 |
| 1715 | MAT | R.C.C. collars NP2 class 150 mm dia | each | 5 | 40.00 | 200.00 |
| 0367 | MAT | Portland Cement (OPC-43 grade) | tonne | 0.006 | 5,156.00 | 30.94 |
| 0983 | MAT | Fine sand (zone IV) | cum | 0.008 | 980.00 | 7.84 |
| 0123 | LAB | Mason 1st classMason 1st class | day | 0.39 | 897.00 | 349.83 |
| 0124 | LAB | Mason 2nd classMason 2nd class | day | 0.39 | 816.00 | 318.24 |
| 0114 | LAB | Beldar | day | 0.78 | 736.00 | 574.08 |
| 0101 | LAB | Bhisti | day | 0.16 | 816.00 | 130.56 |
- TOTAL
- 3,911.49
- Add 1 % Water charges on “W”
- +39.11
- TOTAL
- 3,950.60
- Add GST on “X” (multiplying factor 0.2127)
- +840.29
- TOTAL
- 4,790.89
- Add 15% CPOH on “Y”
- +718.63
- TOTAL
- 5,509.52
- Add Cess @ 1% on “Z”
- +55.10
- Cost of 10 metre
- 5,564.62
- Cost of 1 metre
- 556.46
- SAY
- ₹556.45
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1708
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1708. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.