R/DAR 2023

Providing and laying non-pressure NP2 class (light duty) R.C.C. pipes with collars jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete

150 mm dia. R.C.C. pipe
Item number
19.6.2
Analysis basis
10 metre
Priced inputs
8
Derived rate
₹556.45/ METRE
D-01/RATE ANALYSISITEM 19.6.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.6.2 (Providing and laying non-pressure NP2 class (light duty) R.C.C. pipes with collars jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete : 150 mm dia. R.C.C. pipe) is derived from 8 priced inputs for 10 metre and works out to ₹556.45 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • (in 2 m. length = 5 Nos.)
  • 5 Nos.
  • Cement of 5 joints = 5x0.0008 = 0.004
  • cum = 0.006 tonne
  • Fine sand for 5 joint = 0.0016x5 = 0.008 cum
ANALYSIS OF RATES · ITEM 19.6.2DETAILS OF COST FOR 10 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1701MATR.C.C. pipes NP2 class 150 mm diametre10230.002,300.00
1715MATR.C.C. collars NP2 class 150 mm diaeach540.00200.00
0367MATPortland Cement (OPC-43 grade)tonne0.0065,156.0030.94
0983MATFine sand (zone IV)cum0.008980.007.84
0123LABMason 1st classMason 1st classday0.39897.00349.83
0124LABMason 2nd classMason 2nd classday0.39816.00318.24
0114LABBeldarday0.78736.00574.08
0101LABBhistiday0.16816.00130.56
BUILD-UP TO RATE
TOTAL
3,911.49
Add 1 % Water charges on “W”
+39.11
TOTAL
3,950.60
Add GST on “X” (multiplying factor 0.2127)
+840.29
TOTAL
4,790.89
Add 15% CPOH on “Y”
+718.63
TOTAL
5,509.52
Add Cess @ 1% on “Z”
+55.10
Cost of 10 metre
5,564.62
Cost of 1 metre
556.46
SAY
₹556.45
D-02/SOURCEPRINTED PAGE 1708
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1708

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1708. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSDRAINAGE
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.