Providing and laying non-pressure NP2 class (light duty) R.C.C. pipes with collars jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete

100 mm dia. R.C.C. pipe
Item number
19.6.1
Analysis basis
10 metre
Priced inputs
8
Derived rate
₹507.05/ METRE
D-01/RATE ANALYSISITEM 19.6.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.6.1 (Providing and laying non-pressure NP2 class (light duty) R.C.C. pipes with collars jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete : 100 mm dia. R.C.C. pipe) is derived from 8 priced inputs for 10 metre and works out to ₹507.05 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • (in 2 m. length = 5 Nos.)
  • 5 Nos.
  • Cement of 5 joints = 5x0.00065 =
  • 0.00325 cum = 0.0048 t say 0.005 tonne
  • Fine sand for 5 joint = 0.0013x5 = 0.0065
  • cum = 0.006 cum
ANALYSIS OF RATES · ITEM 19.6.1DETAILS OF COST FOR 10 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1700MATR.C.C. pipes NP2 class 100 mm diametre10220.002,200.00
1714MATR.C.C. collars NP2 class 100 mm diaeach538.00190.00
0367MATPortland Cement (OPC-43 grade)tonne0.0055,156.0025.78
0983MATFine sand (zone IV)cum0.006980.005.88
0123LABMason 1st classMason 1st classday0.32897.00287.04
0124LABMason 2nd classMason 2nd classday0.32816.00261.12
0114LABBeldarday0.63736.00463.68
0101LABBhistiday0.16816.00130.56
BUILD-UP TO RATE
TOTAL
3,564.06
Add 1 % Water charges on “W”
+35.64
TOTAL
3,599.70
Add GST on “X” (multiplying factor 0.2127)
+765.66
TOTAL
4,365.36
Add 15% CPOH on “Y”
+654.80
TOTAL
5,020.16
Add Cess @ 1% on “Z”
+50.20
Cost of 10 metre
5,070.36
Cost of 1 metre
507.04
SAY
₹507.05
D-02/SOURCEPRINTED PAGE 1707
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1707

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1707. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSDRAINAGE
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.