Providing and laying Non Pressure NP-3 class (Medium duty) R.C.C. pipes including collars/ spigot jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete
- Item number
- 19.35.5
- Analysis basis
- 10 metre
- Priced inputs
- 7
- Derived rate
- ₹9,126.20/ METRE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.35.5 (Providing and laying Non Pressure NP-3 class (Medium duty) R.C.C. pipes including collars/ spigot jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete 1200 mm dia RCC pipes. (Laying by manual/ machanical means)) is derived from 7 priced inputs for 10 metre and works out to ₹9,126.20 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- Detail for 10 metre
- MATERIALS :
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 1732 | MAT | RCC pipe 1200 mm dia NP-3 spigot | metre | 10 | 5,564.00 | 55,640.00 |
| 0367 | MAT | Portland Cement (OPC-43 grade) | tonne | 0.034 | 5,156.00 | 175.30 |
| 0983 | MAT | Fine sand (zone IV) | cum | 0.046 | 980.00 | 45.08 |
| 0123 | LAB | Mason 1st classMason 1st class | day | 0.795 | 897.00 | 713.12 |
| 0124 | LAB | Mason 2nd classMason 2nd class | day | 0.795 | 816.00 | 648.72 |
| 0114 | LAB | Beldar | day | 8.67 | 736.00 | 6,381.12 |
| 0101 | LAB | Bhisti | day | 0.67 | 816.00 | 546.72 |
- TOTAL
- 64,150.06
- Add 1 % Water charges on “W”
- +641.50
- TOTAL
- 64,791.56
- Add GST on “X” (multiplying factor 0.2127)
- +13,781.16
- TOTAL
- 78,572.72
- Add 15% CPOH on “Y”
- +11,785.91
- TOTAL
- 90,358.63
- Add Cess @ 1% on “Z”
- +903.59
- Rate per metre
- 9,126.22
- SAY
- ₹9,126.20
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1778
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1778. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.