Providing and laying Non Pressure NP-3 class (Medium duty) R.C.C. pipes including collars/ spigot jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete

1800 mm dia RCC pipes. (Laying by manual/ machenical means)
Item number
19.35.6
Analysis basis
10 metre
Priced inputs
7
Derived rate
₹16,184.00/ METRE
D-01/RATE ANALYSISITEM 19.35.6

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.35.6 (Providing and laying Non Pressure NP-3 class (Medium duty) R.C.C. pipes including collars/ spigot jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete 1800 mm dia RCC pipes. (Laying by manual/ machenical means)) is derived from 7 priced inputs for 10 metre and works out to ₹16,184.00 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Detail for 10 metre
  • MATERIALS :
ANALYSIS OF RATES · ITEM 19.35.6DETAIL OF COST FOR 10 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1733MATRCC pipe 1800 mm dia NP-3 spigotmetre1010,110.001,01,100.00
0367MATPortland Cement (OPC-43 grade)tonne0.0495,156.00252.64
0983MATFine sand (zone IV)cum0.055980.0053.90
0123LABMason 1st classMason 1st classday1.15897.001,031.55
0124LABMason 2nd classMason 2nd classday1.15816.00938.40
0114LABBeldarday13736.009,568.00
0101LABBhistiday1816.00816.00
BUILD-UP TO RATE
TOTAL
1,13,760.49
Add 1 % Water charges on “W”
+1,137.60
TOTAL
1,14,898.09
Add GST on “X” (multiplying factor 0.2127)
+24,438.82
TOTAL
1,39,336.91
Add 15% CPOH on “Y”
+20,900.54
TOTAL
1,60,237.45
Add Cess @ 1% on “Z”
+1,602.37
Rate per metre
16,183.98
SAY
₹16,184.00
D-02/SOURCEPRINTED PAGE 1779
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1779

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1779. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.