Skip to main content
R/DAR 2023

Providing and laying Non Pressure NP-3 class (Medium duty) R.C.C. pipes including collars/ spigot jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete

1000 mm dia RCC pipes. (Laying by manual/ machanical means)
Item number
19.35.4
Analysis basis
10 metre
Priced inputs
7
Derived rate
₹6,656.55/ METRE
D-01/RATE ANALYSISITEM 19.35.4

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.35.4 (Providing and laying Non Pressure NP-3 class (Medium duty) R.C.C. pipes including collars/ spigot jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete 1000 mm dia RCC pipes. (Laying by manual/ machanical means)) is derived from 7 priced inputs for 10 metre and works out to ₹6,656.55 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Detail for 10 metre
  • MATERIALS :
ANALYSIS OF RATES · ITEM 19.35.4DETAIL OF COST FOR 10 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1731MATRCC pipe 1000 mm dia NP-3 spigotmetre104,185.0041,850.00
0367MATPortland Cement (OPC-43 grade)tonne0.0285,156.00144.37
0983MATFine sand (zone IV)cum0.037980.0036.26
0123LABMason 1st classMason 1st classday0.68897.00609.96
0124LABMason 2nd classMason 2nd classday0.68816.00554.88
0114LABBeldarday4.33736.003,186.88
0101LABBhistiday0.5816.00408.00
BUILD-UP TO RATE
TOTAL
46,790.35
Add 1 % Water charges on “W”
+467.90
TOTAL
47,258.25
Add GST on “X” (multiplying factor 0.2127)
+10,051.83
TOTAL
57,310.08
Add 15% CPOH on “Y”
+8,596.51
TOTAL
65,906.59
Add Cess @ 1% on “Z”
+659.07
Rate per metre
6,656.57
SAY
₹6,656.55
D-02/SOURCEPRINTED PAGE 1778
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1778

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1778. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSDRAINAGE
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.