Skip to main content
R/DAR 2023

Providing and laying Non Pressure NP-3 class (Medium duty) R.C.C. pipes including collars/ spigot jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete

900 mm dia RCC pipes
Item number
19.35.3
Analysis basis
10 metre
Priced inputs
7
Derived rate
₹5,377.25/ METRE
D-01/RATE ANALYSISITEM 19.35.3

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.35.3 (Providing and laying Non Pressure NP-3 class (Medium duty) R.C.C. pipes including collars/ spigot jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete 900 mm dia RCC pipes) is derived from 7 priced inputs for 10 metre and works out to ₹5,377.25 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Detail for 10 metre
  • MATERIALS :
ANALYSIS OF RATES · ITEM 19.35.3DETAIL OF COST FOR 10 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1730MATRCC pipe 900 mm dia NP-3 spigotmetre103,395.0033,950.00
0367MATPortland Cement (OPC-43 grade)tonne0.0255,156.00128.90
0983MATFine sand (zone IV)cum0.033980.0032.34
0123LABMason 1st classMason 1st classday0.625897.00560.63
0124LABMason 2nd classMason 2nd classday0.625816.00510.00
0114LABBeldarday3736.002,208.00
0101LABBhistiday0.5816.00408.00
BUILD-UP TO RATE
TOTAL
37,797.87
Add 1 % Water charges on “W”
+377.98
TOTAL
38,175.85
Add GST on “X” (multiplying factor 0.2127)
+8,120.00
TOTAL
46,295.85
Add 15% CPOH on “Y”
+6,944.38
TOTAL
53,240.23
Add Cess @ 1% on “Z”
+532.40
Rate per metre
5,377.26
SAY
₹5,377.25
D-02/SOURCEPRINTED PAGE 1777
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1777

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1777. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.