Providing and laying Non Pressure NP-3 class (Medium duty) R.C.C. pipes including collars/ spigot jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete

600 mm dia RCC pipes
Item number
19.35.2
Analysis basis
10 metre
Priced inputs
7
Derived rate
₹3,401.25/ METRE
D-01/RATE ANALYSISITEM 19.35.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.35.2 (Providing and laying Non Pressure NP-3 class (Medium duty) R.C.C. pipes including collars/ spigot jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete 600 mm dia RCC pipes) is derived from 7 priced inputs for 10 metre and works out to ₹3,401.25 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Detail for 10 metre
  • MATERIALS :
ANALYSIS OF RATES · ITEM 19.35.2DETAIL OF COST FOR 10 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1729MATRCC pipe 600 mm dia NP-3 spigotmetre102,140.0021,400.00
0367MATPortland Cement (OPC-43 grade)tonne0.0165,156.0082.50
0983MATFine sand (zone IV)cum0.022980.0021.56
0123LABMason 1st classMason 1st classday0.46897.00412.62
0124LABMason 2nd classMason 2nd classday0.46816.00375.36
0114LABBeldarday1.83736.001,346.88
0101LABBhistiday0.33816.00269.28
BUILD-UP TO RATE
TOTAL
23,908.20
Add 1 % Water charges on “W”
+239.08
TOTAL
24,147.28
Add GST on “X” (multiplying factor 0.2127)
+5,136.13
TOTAL
29,283.41
Add 15% CPOH on “Y”
+4,392.51
TOTAL
33,675.92
Add Cess @ 1% on “Z”
+336.76
Rate per metre
3,401.27
SAY
₹3,401.25
D-02/SOURCEPRINTED PAGE 1777
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1777

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1777. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.