CPWD Analysis of Rates · Drainage

Providing and laying Non Pressure NP-3 class (Medium duty) R.C.C. pipes including collars/ spigot jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete

450 mm dia RCC pipes

Item number
19.35.1
Analysis basis
Detail of cost for 10 metre
Priced inputs
7
Derived rate
2,676.55 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.35.1 Providing and laying Non Pressure NP-3 class (Medium duty) R.C.C. pipes including collars/ spigot jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete 450 mm dia RCC pipes — is derived from 7 priced inputs for 10 metre and works out to ₹2,676.55 per metre after water charges, GST, CPOH and cess. The full build-up is below.

  • Detail for 10 metre
  • MATERIALS :
CodeInputUnitQuantityRate (INR)Amount (INR)
1728RCC pipe 450 mm dia NP-3 spigotMaterialmetre101,605.0016,050.00
0367Portland Cement (OPC-43 grade)Materialtonne0.0125,156.0061.87
0983Fine sand (zone IV)Materialcum0.017980.0016.66
0123Mason 1st classMason 1st classLabourday0.375897.00336.38
0124Mason 2nd classMason 2nd classLabourday0.375816.00306.00
0114BeldarLabourday2.41736.001,773.76
0101BhistiLabourday0.33816.00269.28
TOTAL
18,813.95
Add 1 % Water charges on “W”
188.14
TOTAL
19,002.09
Add GST on “X” (multiplying factor 0.2127)
4,041.74
TOTAL
23,043.83
Add 15% CPOH on “Y”
3,456.57
TOTAL
26,500.40
Add Cess @ 1% on “Z”
265.00
Rate per metre
2,676.54
Say
2,676.55

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1776. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.