Skip to main content
R/DAR 2023

Providing and laying Non Pressure NP-3 class (Medium duty) R.C.C. pipes including collars/ spigot jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete

450 mm dia RCC pipes
Item number
19.35.1
Analysis basis
10 metre
Priced inputs
7
Derived rate
₹2,676.55/ METRE
D-01/RATE ANALYSISITEM 19.35.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.35.1 (Providing and laying Non Pressure NP-3 class (Medium duty) R.C.C. pipes including collars/ spigot jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete 450 mm dia RCC pipes) is derived from 7 priced inputs for 10 metre and works out to ₹2,676.55 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Detail for 10 metre
  • MATERIALS :
ANALYSIS OF RATES · ITEM 19.35.1DETAIL OF COST FOR 10 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
1728MATRCC pipe 450 mm dia NP-3 spigotmetre101,605.0016,050.00
0367MATPortland Cement (OPC-43 grade)tonne0.0125,156.0061.87
0983MATFine sand (zone IV)cum0.017980.0016.66
0123LABMason 1st classMason 1st classday0.375897.00336.38
0124LABMason 2nd classMason 2nd classday0.375816.00306.00
0114LABBeldarday2.41736.001,773.76
0101LABBhistiday0.33816.00269.28
BUILD-UP TO RATE
TOTAL
18,813.95
Add 1 % Water charges on “W”
+188.14
TOTAL
19,002.09
Add GST on “X” (multiplying factor 0.2127)
+4,041.74
TOTAL
23,043.83
Add 15% CPOH on “Y”
+3,456.57
TOTAL
26,500.40
Add Cess @ 1% on “Z”
+265.00
Rate per metre
2,676.54
SAY
₹2,676.55
D-02/SOURCEPRINTED PAGE 1776
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1776

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1776. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSDRAINAGE
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.