Providing and fixing S.W. intercepting trap in manholes with stiff mixture of cement mortar 1:1 (1 cement : 1 fine sand) including testing of joints etc. complete

100 mm dia
Item number
19.34.1
Analysis basis
Details of cost of 10 nos.
Priced inputs
9
Derived rate
₹441.40
D-01/RATE ANALYSISITEM 19.34.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 19.34.1 (Providing and fixing S.W. intercepting trap in manholes with stiff mixture of cement mortar 1:1 (1 cement : 1 fine sand) including testing of joints etc. complete : 100 mm dia) is derived from 9 priced inputs and works out to ₹441.40 after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 19.34.1DETAILS OF COST OF 10 NOS
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7128MATS.W. intercepting trap 100 mm diaeach10200.002,000.00
9977MATCarriage of trapL.S.10.42.2723.61
0367MATPortland Cement (OPC-43 grade)tonne0.0135,156.0067.03
0983MATFine sand (zone IV)cum0.01980.009.80
1881MATSpun yarnkilogram0.961.0054.90
0123LABMason 1st classMason 1st classday0.2897.00179.40
0124LABMason 2nd classMason 2nd classday0.2816.00163.20
0114LABBeldarday0.6736.00441.60
0101LABBhistiday0.2816.00163.20
BUILD-UP TO RATE
TOTAL
3,102.74
Add 1 % Water charges on “W”
+31.03
TOTAL
3,133.77
Add GST on “X” (multiplying factor 0.2127)
+666.55
TOTAL
3,800.32
Add 15% CPOH on “Y”
+570.05
TOTAL
4,370.37
Add Cess @ 1% on “Z”
+43.70
Cost of 10 nos.
4,414.07
Cost of one no.
441.41
SAY
₹441.40
D-02/SOURCEPRINTED PAGE 1775
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1775

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1775. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSDRAINAGE
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.